Update for week ending May 3, 2024
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical & electrical work continues on level zero, level one, level two, and level
three. Interior metal stud framing continues on level zero, level one, level two and
level three. Exterior metal stud framing continues. Topping out is scheduled for May
22.
Autism Student Support Center, West Plains Campus
Adam Shuler, Project Manager
Steel installation will continue for the next several weeks. Structural stud framing
will start in the coming weeks with the parapets and then exterior walls. Once the
parapets are framed the roof will be installed.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
The third concrete slab pour for level one was poured this week. This completes the
level one concrete pours except for a small area on the west side for the new training
lab storage. Structural steel erection has begun on the previously poured slab areas,
which will be the new entrance and lobby area. Underground electrical conduit and
basement electrical equipment work continues. Under slab plumbing trench drain work
continues. Mechanical, electrical, and plumbing raceways in the existing building
for electric and data conduit for doors and fire alarm are in progress.
Agricultural Innovation Hub, Darr Agricultural Center
Shanon Mitchell, Project Manager
Under slab electrical and plumbing work continues. Concrete slab edge forming is in
progress in preparation for concrete slab pours next week.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Sidewalk replacement to commence the week after graduation.
MSU Baseball Training Facility
Adam Shuler, Project Manager
Floor installation is complete and floor base will be installed this week. Ceilings
have been installed and paint touch up will occur this week. All work will be complete
next week with the exception of the glass storefront door to weightroom.
Turf Replacement, Allison South Stadium
Eric Easter, Project Manager
Submittals have been reviewed and approved. The contractor is securing materials for
the project. A kick-off meeting occurred this week. Staging, dumpster location, and
project schedule were reviewed. Work will commence after graduation.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
The north gym bleacher removal has been completed as well as the wall repair in the
West Gym and the installation of electrical wiring, supply piping, and HVAC piping/ductwork
in the new locker room. Upcoming activities include the installation of hydronic
water lines and hallow metal door frames as well as the cleaning and painting of the
north gym wall. The domestic water tie-in is scheduled for next week. Further work
in the north and south gyms, and the east and west decks will begin following graduation.
Roof Replacement, Garst Dining Center
Eric Easter, Project Manager
Project submittals are being reviewed. The contractor is securing all of the materials
for the project. A kick-off meeting occurred this week. Work will commence after graduation.
Printable weekly updates
- May 3, 2024
- April 26, 2024
- April 19, 2024
- April 12, 2024
- April 5, 2024
- March 29, 2024
- March 22, 2024
- March 15, 2024
- March 8, 2024
- March 1, 2024
- February 23, 2024
- February 16, 2024
- February 9, 2024
- February 2, 2024
- January 26, 2024
- January 19, 2024
- January 12, 2024