Update for week ending December 20, 2024
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical & electrical rough-in and finish work continues on all levels. The permanent
transformer is scheduled to be on site in the upcoming weeks. The outage for installation
will not occur until Spring. Gypsum board installation and finishing continues on
all levels. Preliminary and final painting continues on all levels. Curtain wall installation
and Metal & Glass Fiber Reinforced Concrete work is scheduled to be complete by the
end of December. Roofing work for the new addition is nearly complete. The auditorium
roof is scheduled to be complete as the curtain wall is completed. Exterior hardscaping
continues. Lab casework installation on level two and three continues. Cabling continues
on level two. The Dean’s Suite and Student Success Suite furniture installation and
move-in is complete. For the existing building renovation, mechanical & electrical
rough-in continues. Plumbing and hydronic piping continues.
Autism Student Support Center, West Plains Campus
Adam Shuler, Project Manager
The toilet partitions and accessories have been installed and the interior glazing
installation is nearly complete. Flooring installation is complete, and door hardware
is being installed this week. The ceiling grid, acoustic baffles, and lights installation
is nearly complete. The installation of exterior stone and brick cladding will be
complete this week.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
Acoustical tile ceiling grid installation has begun. Painting and tile work continues.
Electrical work installing lights, HVAC control work, and fire sprinkler head drops
are progressing. Ductwork insulation is wrapping up. Interior concrete floor grinding
and sealing is nearly complete. Stairwell block wall installation is complete and
being cleaned this week. The north sidewalk is installed, and the high-performance
concrete building panel installation has commenced.
Agricultural Innovation Hub, Darr Agricultural Center
Shanon Mitchell, Project Manager
A punch list walkthrough occurred this week.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Campus Construction Team has completed their work. The Job Order Contractor has submitted
final documents for the remainder of the work.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
The primary renovation work has been completed. Work is underway to convert three
unused concession stands and one racquetball court into storage space. Drywall installation
is mostly complete pending receipt of the new doors. Mudding is to occur this week.
No work will occur during Commencement. Some work may occur over winter break and
will fully resume after the break.
Refurbish and Renovate Main Elevator, Carrington Hall
Eric Easter, Project Manager
The elevator has been taken out of service and will be out until mid-February. The
contractors are currently removing ceiling tiles and bringing piping in to connect
to the new controllers. The controller equipment has been installed and a large portion
of the mechanical, electrical, and plumbing has been completed. Over the break, contractors
will focus on removing the cab and finishes as well as continual work to connect the
new equipment.
Renovation of First and Second Floors, Kings Street Annex
Eric Easter, Project Manager
The contractor is completing punch list items as well as a few additional changes
to the project. Faculty have moved in.
Replace Roof, Hammons Hall for the Performing Arts
Yo Satake, Project Manager
For Roof C, the contractor has finished putting down the 2-ply membranes. Final coating
with gravel to be applied when the temperature allows next year. For the low roofs,
insulation replacement work is in progress. Final coating will occur when the temperature
allows next year.
Renovate Classrooms and Hallways, Greenwood Laboratory School
Chelsea Beck, Project Manager
Drywall and painting continue. Hallway and ceiling work has commenced. Work will continue
over winter break.
Renovation of Room 105, Meyer Library
Adam Shuler, Project Manager
Construction started this week, and a dust barrier has been installed. Demolition
in the existing space will start this week, and wall framing will begin next week.
Plumbing installation for a new water fountain will occur this week.
Third Floor Buildout, Jordan Valley Innovation Center
Shanon Mitchell, Project Manager
The contractor plans to mobilize after winter break. Submittals are in progress.
Printable weekly updates
- December 20, 2024
- December 13, 2024
- December 6, 2024
- November 22, 2024
- November 15, 2024
- November 8, 2024
- November 1, 2024
- October 25, 2024
- October 18, 2024
- October 11, 2024
- October 4, 2024
- September 27, 2024
- September 20, 2024
- September 13, 2024
- September 6, 2024