Update for week ending April 24, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is on track for completion. The final Commissioning
Report has been issued and deficiencies are being addressed. Final furnishings will
be installed by mid-May. A warranty review was held. A preliminary list of warranty
items has been submitted by the consultants for review and is scheduled for completion
mid-May.
For the existing building renovation (Phase II):
- Level 1, 2, 3 (South), and 4 (North): Mechanical/Electrical work is complete except
for commissioning. The Commissioning Agent was onsite last week, with corrections
ongoing. Door/hardware is near completion. Card access to follow.
- Level 3 North: A punch list review is scheduled for April 27. Mechanical/Electrical
work is complete except for controls. Room finishes are complete. Final cleaning has
commenced. Completion is scheduled for late April with room moves scheduled for the
first two weeks of May.
- Level 4 South: Mechanical/Electrical work continues. Completion is scheduled for early
June with room moves scheduled for mid-June.
- Atrium: The pit has been substantially cleared to begin carpeting.
- Roofing: scheduled to be completed by the first of June (weather pending).
- Exterior: Landscaping is scheduled to commence in May. Briggs Street final asphalt
topping is scheduled for early June.
- Additional work: The replacement elevator is scheduled to commence early to mid-May.
Fume Hood installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Craig Hall painting continues in the new student lounge, restrooms, and Box Office.
Masonry veneer installation is wrapping up at the scene shop addition. Mechanical,
electrical, and plumbing installation continues in the scene shop addition. The new
building drywall installation and finishing continue throughout. The new building
mechanical, electrical, and plumbing rough-in continues. The new building exterior
soffit sheathing installation and weather barrier continues. Work continues on the
dumpster/electrical courtyard concrete walls.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
Punch list items are being completed. A punch list review for the second floor will
occur next week.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Hard lid ceiling work has commenced at the north stairs. The remaining exterior glass
units are being installed. Acoustical ceiling grid installation continues at the second-floor
offices. Drywall installation and finishing continue throughout the building. Interior
electrical, mechanical, and plumbing rough-in continue throughout the building. Electrical
finishes are being installed on the second-floor offices. Elevator installation is
wrapping up. Exterior terracotta cladding installation continues at the north, south,
and east facades. Exterior insulation is being installed around the Event Hall to
prepare for conditioning that space. Exterior soffits at the Executive Board Room
and Living Room are complete.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
This project is substantially complete. There will be additional repairs to the awning.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Demolition work on level 2 is nearing completion. The walls and ceilings have been
removed, and HVAC and electrical removal is wrapping up next week. A fully enclosed
trash chute has been installed on the NW corner of the building to safely remove demolished
materials from Level 2. Ductwork installation and wall layouts will begin on level
2 next week. Abatement work on Level 1 is complete and demolition on level 1 has begun
in earnest.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make periodic site visits for verifications.
Submittal reviews continue. The contractor plans to move onsite mid-May.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
The installation of furniture is substantially complete with minor adjustments forthcoming.
Data installation is scheduled for completion this week. The contractor has completed
most of the work and they’re now addressing anticipated punch list items, with painting
scheduled this week. The breakroom flooring will be replaced prior to move-in due
to damage that occurred during the HVAC start-up process. The punch list review is
scheduled for April 27, and the department will move into their space the first week
of May.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Ceilings and new storefront glass are being installed this week. Plumbing fixtures
installations are in progress, and asphalt repairs and patching have been completed.
A punch list review is scheduled for May 7.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting are in progress on the west wing west
side and north side of Freudenberger House. The Contractor continues work at Blair
House on the north side, and the west side of Shannon House. The work will continue
into Summer 2026.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
Submittal reviews are in progress. Work is anticipated to begin mid-May. The anticipated
project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor plans to mobilize in June.
Printable weekly updates
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026