Update for week ending January 16, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & electrical commissioning continues to be on hold due to graphics issues.
A process to complete commissioning has been established. Monument signage lighting
final installation is scheduled for mid-January. A short list of remaining items is
being addressed and scheduled for January and February. Additional items in progress
include furnishings, auditorium lighting, and miscellaneous lab equipment.
For the existing building renovation (Phase II):
- Level 1: Mechanical and electrical are complete except for commissioning. Final lab
shifts are complete. Final room finishing is underway. Door and hardware commissioning
has commenced and near completion.
- Level 2 South: Substantially complete except for lab entry painting/tackboard and
card access. Door and hardware installation have commenced and near completion.
- Level 2 North: Mechanical and electrical work near completion except for commissioning.
Office and lab moves are complete or ongoing in preparation for classes. Corridors
are near completion.
- Level 3 South: Substantially complete except for lab entry painting/tackboard and
card access. Door and hardware installation have commenced and near completion.
- Level 3 North: Demolition has commenced.
- Level 4 North: Room demolition continues. Mechanical and electrical work have commenced.
- Roofing has commenced and is near completion.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
The Craig Hall addition concrete block installation is wrapping up. The Craig Hall
addition roof installation continues. Craig Hall drywall finishing is wrapping up
on the second floor. Craig Hall floor leveling is complete in the new student lounge.
New building exterior sheathing is wrapping up while water proofing continues. New
building interior framing continues. New building overhead mechanical, electrical,
and plumbing rough-in continues. New building curtainwall installation has commenced,
and sawtooth window framing has been installed at the south façade. New building masonry
veneer is being installed on the north façade.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The 4th floor is complete and the office furniture has been installed. Carpet installation
is being completed in the first-floor lobby. Touch up painting continues in all areas.
The wood wall coverings are being installed. Demolition has begun in the 2nd and
3rd floor offices. Anticipated move in date is January 26th, with partial occupancy taking place on January 20th.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
Drywall repairs were made over winter break. The contractor is currently working on
a few punch list items.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Interior framing continues. Interior electrical, mechanical, and plumbing rough-in
continue throughout the building. Roof installation is wrapping up. Curtainwall installation
is 90% complete, and glass has been installed in the smaller windows along National
Ave. Exterior weather barrier and liquid flashing continue around the building. The
rooftop air handler installation is complete.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
Crews have moved to the last section on the Northside and Westside of the building.
All previous work on the Northside and Westside is complete. The contractor continues
to work on real sealing the windows and construction joints on each floor. The cold
weather has delayed progress.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Flooring installation continues along with painting in offices. Ceilings are being
installed on the Mezzanine level next week. Glass marker boards have been installed
throughout phase 1 areas. Tile installation is complete in the Mezzanine level restrooms
and toilet accessories have been mounted. The mezzanine wall in the lobby has been
removed, and structural steel will be installed next week. The electrical conduit
to the new basement panels has been installed and the switch gear will be finished
next week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make site visits for verifications. We are currently
working on reviewing submittals from the contractor. Selective demolition took place
over winter break.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
Demolition is mostly complete, though some items remain to prevent disrupting the
building temporarily. Dumpster delays slowed disposals but pick up is scheduled and
then the space will be cleared out further. Ductwork and HVAC unit deliveries are
expected this week or early next week. Two proposals for unforeseen conditions have
been received with a third proposal pending. Pricing will be reviewed and rough-in
work will continue.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Concrete pour back for the plumbing and electrical work is taking place this week.
Rough-in for the HVAC work has started. Submittal reviews are in progress. Anticipated
project completion is at the end of the Spring 2026 semester.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Work on the east and south elevations of Freudenberger House have started. Work will
continue into the summer.
Printable weekly updates
- January 16, 2026
- January 9, 2026
- December 19, 2025
- December 12, 2025
- December 5, 2025
- November 21, 2025
- November 14, 2025
- November 7, 2025
- October 31, 2025
- October 24, 2025
- October 17, 2025
- October 10, 2025
- October 3, 2025