Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending March 27, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is on track for completion. The final visit
with the Commissioning Agent is scheduled for the next two weeks. Final furnishings
will be installed by the middle of May. A preliminary list of warranty items has been
submitted by consultants for review. The schedule for completion is mid-May.
For the existing building renovation (Phase II):
- Level 1, 2, 3 (South), & 4 (North): Mechanical/Electrical work is complete except
for commissioning. Preliminary checklists are underway. Door/hardware is still pending
due to door delays. Card access to follow.
- Level 3 North: Mechanical/Electrical work continues. Room finishes continue. Ceiling
grid work has commenced. Completion is scheduled for late April with moves scheduled
for the first two weeks of May.
- Level 4 South: Demolition is near completion. Electrical/Mechanical work has commenced.
Completion is scheduled for early June with moves scheduled for mid-June.
- Atrium: Work on the ceiling is complete. Scaffolding has been removed and replaced
at the south window wall to complete work. Scheduled to be removed in 3 weeks.
- Roofing: the south side roofing has commenced.
- Exterior: Landscaping is scheduled to commence mid-April/May. Briggs Street final
asphalt topping is scheduled for June.
- Other: The replacement elevator is scheduled to commence the beginning of May. Fume
Hood installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Craig Hall interior ramp work continues. Craig Hall terrazzo installation continues.
Craig Hall drywall installation and finishing continues at the first floor. The new
building drywall installation continues throughout. The new building mechanical, electrical,
and plumbing rough-in continues. The new building masonry veneer installation continues
at the west façade and scene shop addition. Awaiting remaining exterior glass units
for the new building.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
Punch list items are being completed on the first floor. The third floor punch list
review was conducted this week and the contractor is working on completing those items.
The second floor work is wrapping up. The contractor will be reseeding the laydown
area this week. The punch list review for the second floor will be later in April.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing continue throughout the Event Hall and at the second
floor offices. Interior electrical, mechanical, and plumbing rough-in continues throughout
the building. Elevator installation has commenced. Awaiting remaining exterior glass
units. Exterior terracotta cladding installation has commenced on the east façade.
Window trim/flashing installation continues and is wrapping up at the east façade.
The trash enclosure and golf cart storage building foundation work has commenced.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
Work on the building exterior is complete. The roofing portion of the work continues.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Minor work in the basement and classroom 151 was completed last week. On the Mezzanine,
the control valve replacement is complete and HVAC testing and balancing is underway.
Painting and flooring installation is complete in the lobby and common areas on the
first floor. Furniture installation in the lobby and common areas will finish up this
week. The Mathematics Department and Computer Science Department moved into their
new offices in the phase one areas.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make periodic site visits for verifications.
Submittal reviews continue. The contractor plans to move onsite mid-May.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
The final pressure test was completed successfully. Hydronic pipe insulation and
electrical work above the ceiling have been completed. The engineer’s recent inspection
report comments have been fully addressed and the above ceiling inspection is forthcoming.
Ceiling grid work has begun, and painting is scheduled for early next week.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Painting and wall panel installations are in progress. Project completion is anticipated
for mid-May.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting continues on the west wing courtyard
side and east wing east side of Freudenberger House. The Contractor continues work
at Blair-Shannon House on the south and west elevations. The work will continue into
Summer 2026.
Printable weekly updates
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026
- December 19, 2025
- December 12, 2025
- December 5, 2025