Update for week ending October 31, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical and electrical commissioning is complete except for two items which are
in process of completion. The Project Engineer is working with the Commissioning Agent
and JCI to identify the issues with completion. Final furnishings installation is
complete. Interior building signage and monument signage lighting final installation
are scheduled for mid-November. Strobic fan silencers are scheduled to be installed
the week of Thanksgiving. Remaining items are currently being addressed and are near
completion. Phase I is scheduled to be complete by the end of December. For the existing
building renovation (Phase II):
- Level 1: Mechanical/electrical work is nearly complete.
- Level 1: Rooms are nearing completion, pending the lab moves.
- Level 1: Floor polishing has commenced. Scheduled to be completed this week.
- Level 2 South: Substantially complete except for ceiling tile placement and doors/hardware.
- Level 2 North: Mechanical/electrical work near completion.
- Level 2 North: Rooms near completion.
- Level 2 North: Corridors near completion. Floor polishing is scheduled to commence
next week.
- Level 3 South: Substantially complete except for ceiling tile placement and doors/hardware.
- Level 4 North: Corridor ductwork demolition is complete. Room demolition continues.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Floor leveling in the new Craig Hall Student Lounge continues. Craig Hall addition
under slab MEP rough-in is complete. Craig Hall interior MEP rough-in continues. Excavation
continues within Craig Hall for the new ADA ramp on the north side of Coger Theatre.
The second-floor concrete pour is complete. Exterior framing and sheathing have commenced.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The 4th floor is complete. The punch list inspection will occur next week. Ceramic
tile and LVT are completed. Additional floor prep is needed in some areas where the
carpet is being installed. Glass doors will arrive this week, and installation will
occur next week. All the wooden doors have been painted and installed. The remaining
sound booth was installed last week. Painting on the 1st floor will be finished next
week.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
All skylight and roof work is complete. Drywall repairs are being scheduled.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Steel detailing and decking are wrapping up. Framing and sheathing installation continues
throughout the building. Roof drain piping installation is complete. Interior framing
continues. Interior electrical wall rough-in continues. Roof installation has commenced
at the Event Center. MEP rough-in continues in the mechanical room.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
Work crews have been delayed by the rain. Stucco columns on the North side have been
painted. The center section has been resealed. Crews are continuing their work on
the Northeast section. The second crew on the west side has completed the Northwest
corner section of the building and continues to work on the center section between
the stucco columns.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The old stairs from the Lobby to the Mezzanine have been removed and the new stairs
are being installed this week. Drywall installation is complete, and finishes will
begin next week on the Mezzanine Level. Vertical stud framing is almost complete at
Level 1 and MEP rough-in has started. Duct penetrations are complete on the Mezzanine
Level and steel supports will be installed soon. Door frames are starting to be installed
on Level 1 and FCU installation has begun. The level 1 concrete pour will occur this
week at the existing pipe trench.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator Contractor has conducted their preliminary field survey. We are working
on getting submittals from the Contractor.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
The removal of mobile shelving, shelving track, and panel furniture is scheduled to
be completed this week. Abatement work will resume next week to include the removal
of carpet and two layers of VCT. Further asbestos testing is ongoing to ensure that
all materials are appropriately addressed.
Printable weekly updates
- October 31, 2025
- October 24, 2025
- October 17, 2025
- October 10, 2025
- October 3, 2025
- September 26, 2025
- September 19, 2025
- September 12, 2025
- September 5, 2025
- August 29, 2025
- August 22, 2025
- August 15, 2025
- August 8, 2025
- August 1, 2025