Update for week ending April 10, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is on track for completion. The Commissioning
Agent is onsite this week. Final furnishings will be installed by mid-May. A warranty
review was held this week. A preliminary list of warranty items has been submitted
by the consultants for review and is scheduled for completion mid-May.
For the existing building renovation (Phase II):
- Level 1, 2, 3 (South), and 4 (North): Mechanical/Electrical work is complete except
for commissioning. The Commissioning Agent is onsite this week. Door/hardware is still
pending due to door delays. Card access to follow.
- Level 3 North: Mechanical/Electrical work is near completion. Room finishes and ceiling
grid installation continues. Completion is scheduled for late April with room moves
scheduled for the first two weeks of May.
- Level 4 South: Mechanical/Electrical work has commenced. Completion is scheduled for
early June with room moves scheduled for mid-June.
- Atrium: Scaffolding has been removed.
- Roofing: Work is scheduled to be completed by the first of June.
- Exterior: Landscaping is scheduled to commence in May. Briggs Street final asphalt
topping is scheduled for early June. Completion of the building cleaning is scheduled
for late April or early May.
- Additional work: The replacement elevator is scheduled to commence early to mid-May.
Fume Hood installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Craig Hall painting continues in the new student lounge, restrooms, and Box Office.
Masonry veneer installation continues at the scene shop addition. New building drywall
installation and finishing continue throughout. The new building mechanical, electrical,
and plumbing rough-in continues. The new building exterior soffit sheathing installation
continues.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The first-floor punch list items are being completed. The third-floor punch list
review has occurred, and the contractor is working through those items. The second-floor
punch list review will occur mid-April. The contractor will be reseeding the laydown
area this week.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Painting continues at the Event Hall and second floor offices. Acoustical ceiling
grid installation has commenced on the second-floor offices. Drywall installation
and finishing continue throughout the building. Interior mechanical, electrical, and
plumbing rough-in continue throughout the building. Elevator installation continues.
Exterior terracotta cladding installation continues at the north, south, and east
facades. Exterior insulation continues at the south façade. The trash enclosure and
golf cart storage building foundation work is complete and slabs have been poured.
The new sidewalk on the west side of the building is partially poured. Exterior soffits
are being installed at the executive board room and living room.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
Work on the building exterior is complete. The roofing portion of the work is complete.
The contractor is working on completing the lightning protection this week.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Phase 2 began with demolition work on Level 2. A fully enclosed trash chute has been
installed on the NW corner of the building to safely remove demolished materials from
Level 2. Abatement work on Level 2 will be complete this week and will begin on Level
1 next week. On the Mezzanine Level, HVAC testing and balancing is finishing up. Furniture
installation in the lobby and common areas is now complete.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make periodic site visits for verifications.
Submittal reviews continue. The contractor plans to move onsite mid-May.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
Recently completed work includes control work, insulation installation, above ceiling
inspection items, fire alarm testing, fire alarm labels set, patched CMU walls, painting
in the hallway, millwork installation, and putting power to the lights and testing
outlets. Ongoing tasks that are near completion include electrical work, ceiling
grid installation, light fixture installation, wall paint, flooring install, and the
installation of ceiling registers and grilles. Upcoming work includes the installation
of ceiling tiles, the startup of fan coil units and testing and balancing, and the
final installation of countertops and associated plumbing fixtures. The installation
of furniture is set to begin next week with data and electrical work.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Epoxy floor work is in progress. Project completion is anticipated for mid-May.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting continues on the west wing courtyard
side and east wing east side of Freudenberger House. The Contractor continues work
at Blair-Shannon House on the south and west elevations. The work will continue into
Summer 2026.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
Submittal reviews are in progress. Work is anticipated to begin mid-May. The anticipated
project completion is mid-July.
Printable weekly updates
- April 10, 2026
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026