Update for week ending April 11, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Punch list review for the link to the new addition and the auditorium is scheduled
for mid-May. Mechanical & electrical commissioning continues. The architectural punch
list is nearing completion. Interior door and hardware installation is nearing completion.
Exterior soffit rework is nearing completion. Exterior hardscaping is nearing completion.
Topsoil installation is complete. Planting and mulching have commenced. MSU Telecommunications
cabling continues on all Levels. CRPM work has commenced. Ceiling work has commenced.
For the existing building renovation, mechanical and electrical work continues. Plumbing
and hydronic piping is complete. Interior wall patching has commenced. Exterior concrete
patching and cleaning continues.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
The project punch lists have been issued to the contractor. Owner walkthroughs and
corrective work is in progress. Landscaping work has begun. Furniture installation
is scheduled for this month.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
The Job Order Contractor has submitted their work plan for review.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
Work at the locker room and weight room has been completed. Construction at the three
lobby storage areas is complete, pending keying. A few punch list items remain for
the fourth storage area in addition to keying.
Replace Roof, Hammons Hall for the Performing Arts
Eric Easter, Project Manager
The new roof has been installed. All other roofs that were to have a fluid applied
coating have been completed except for roof G. Minor touch-ups will be completed
this week along with roof G, weather permitting.
Renovate Classrooms and Hallways, Greenwood Laboratory School
Chelsea Beck, Project Manager
Work in the hallways is nearly complete. Wrapping up the current classroom renovation.
The contractor will begin work on the next classroom next week.
Third Floor Buildout, Jordan Valley Innovation Center
Shanon Mitchell, Project Manager
Drywall finishing is in progress. Work continues with electrical overhead rough-in,
plumbing in-wall rough-in and above ceiling piping installation on the second floor,
and HVAC spiral ductwork installation.
Turf Replacement, Plaster Stadium
Bethany Henry, Project Manager
Construction is anticipated to begin next week. Construction will begin with removal
of the existing turf and delivery of materials to the project site.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Pier drilling continues. Two drill rigs are being utilized. Pier rebar cages are being
fabricated onsite. Fourteen of the fifty-one piers have been poured. The building
mockup board formed concrete wall has been poured. Wall framing will proceed next.
Craig Hall asbestos abatement and demolition will begin mid-May.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
Demolition of the walls and electrical is nearly complete. Demolition of mechanical,
electrical, and plumbing has begun. Removal of the sound booths will begin next week.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
Skylights have been ordered, and a delivery date is not yet established. Roofing
and skylight work is to be completed simultaneously, with an anticipated start date
to occur after spring commencement.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Asphalt removal at the building footprint is complete. Excavation continues. The contractor
is preparing for underground chilled water work to begin in early May. The contractor
is preparing for underground electrical work to begin in late April.
Lighting Improvements, Plaster Stadium
Bethany Henry, Project Manager
Submittals for the project are in progress. Construction is anticipated to begin May
12.
Printable weekly updates
- April 11, 2025
- April 4, 2025
- March 28, 2025
- March 21, 2025
- March 14, 2025
- March 7, 2025
- February 28, 2025
- February 21, 2025
- February 14, 2025
- February 7, 2025
- January 31, 2025
- January 24, 2025
- January 17, 2025