Weekly Project Updates

 

The Office of Planning, Design and Construction is pleased to share weekly project updates with the campus, the community, and beyond. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates and previous updates are available at the bottom of this page. If you would like additional details, or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignandConstruction@Missouristate.edu. Thank you for your interest in projects at Missouri State University.

Update for Week Ending February 16, 2018

For a printable version of this week’s project updates, click here.

New Elevator Installation, Kentwood Hall

Jerry Compton, Project Manager

Work on the installation of the elevator continues.


New Health & Wellness Center

Jerry Compton, Project Manager

The installation of doors is nearly completed. The installation of casework continues. The installation of floorcoverings is scheduled for completion by February 19. Installation of the tile is nearly complete on the main stairway. The installation of the glass for the main stair is currently in progress. Work has begun on construction of the new driveways and site work.


Renovation of Hass-Darr Hall, West Plains Campus

RobRoy Viau, Project Manager

The moisture barrier on the exterior of the foundation is being applied.  The rough grading of the site is complete.  Cast stone is being installed on the monument wall. 


Renovation, Hill Hall

Mark Wheeler, Project Manager

On the exterior of the building the gutter repairs continue.  At the first floor wall framing continues along with the installation of mechanical equipment and piping, plumbing rough-in and electrical routing.  HVAC rough- in piping installation above ceiling continues in the lecture halls.  On the second floor drywall finishing continues along with the installation of steel sub-framing at the corridor benches.  On the third floor final paining is occurring along with the installation of glass at office sidelites.  Acoustical ceiling grid installation has begun in conjunction with lighting install.  On the fourth floor stud wall framing continues along with the installation of soffits.  All batt insulation has been installed allowing the sheet rock installation to occur over the next few weeks.


Renovate South Elevator, Professional Building

Jerry Compton, Project Manager

The elevator equipment is in production.


Locker Room Addition, Greenwood Laboratory School

Jerry Compton, Project Manager

Excavation for footings and underslab construction continues. Work to re-route electrical feeders that serve a portion of the existing building is underway. Construction of the masonry walls has begun.

  • New Wellness Center Construction

  • Renovation at Ellis Hall

  • Addition at Glass Hall

  • Renovation at Hass-Darr Hall

Printable Version of Updates: