Update for week ending November 15, 2024
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical & electrical rough-in work continues on all levels. Finish work is occurring
on level zero and level one. Gypsum board installation continues on level one and
level four. Final painting in select locations continues on level one, and four. Curtain
wall installation and Metal & Glass Fiber Reinforced Concrete work is scheduled to
be completed the beginning of December. Roofing work is scheduled to be complete by
the end of November. Exterior hardscaping has commenced. Lab casework installation
on level two continues. Networking and Telecommunications is installing cabling. For
the existing building renovation, mechanical & electrical rough-in continues. Plumbing
and hydronic piping has commenced.
Autism Student Support Center, West Plains Campus
Adam Shuler, Project Manager
Interior painting continues and is approximately 90% complete. The interior doors,
sidelites, and other interior glazing installation will be complete next week. The
interior finishes, ceiling grid, acoustic baffles, and lights are currently being
installed. The installation of exterior stone and brick cladding is ongoing, and exterior
handrails have been installed. The asphalt paving has been installed and the concrete
site work is complete.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
Interior wall framing is nearly complete and drywall installation and finishing continues.
Electrical work continues on raceways and wire pulling. Ductwork installation, plumbing
piping, air compressor line, insulation, and fire sprinkler piping is nearing completion.
Painting continues on the ceilings and stairs. HVAC control work is in progress. Roofing
at the stairwell is nearing completion. Concrete drive paving continues on the west
side of the building.
Agricultural Innovation Hub, Darr Agricultural Center
Shanon Mitchell, Project Manager
Lighting and plumbing fixture installations continue. HVAC start-up is planned for
next week pending power to panels this week, and controls work is in progress. Overhead
doors have been installed. Door hardware installation and specialty installations
continue. Welding booths are installed and ready for paint. Site concrete pours are
scheduled for next week.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Campus Construction Team has completed their work. The Job Order Contractor will be
preparing a new schedule for the remainder of the work.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
The primary renovation work has been completed. Additional work to convert three unused
concession stands and one racquetball court into storage space is expected to begin
this month.
Refurbish and Renovate Main Elevator, Carrington Hall
Eric Easter, Project Manager
The new fan coil unit has been installed. The new electrical panel has been re-fed,
and the new fire rated door has been installed. The hoist way work has been completed.
The contractor will begin to move some of the elevator equipment into the room. The
main elevator replacement will occur in December.
Renovation of First and Second Floors, Kings Street Annex
Eric Easter, Project Manager
The second-floor punch list items are to be completed by next week. Furniture installation
on the second floor has been delayed due to pending punch list items. The first-floor
carpet installation is complete. Miscellaneous items, door hardware, and painting
has commenced. Another punch list review will occur this week. Furniture installation
will continue next week for the first floor and remaining portion of the second floor.
Replace Roof, Hammons Hall for the Performing Arts
Yo Satake, Project Manager
Roofing work has begun. The contractor is removing most of the existing roof from
the main auditorium roof and coating the low roofs.
Renovate Classrooms and Hallways, Greenwood Laboratory School
Chelsea Beck, Project Manager
Materials are being ordered. Work is anticipated to begin in late November.
Renovation of Room 105, Meyer Library
Adam Shuler, Project Manager
Submittals and shop drawings are being reviewed and materials will be ordered. Construction
will begin on site after the fall semester.
Printable weekly updates
- November 15, 2024
- November 8, 2024
- November 1, 2024
- October 25, 2024
- October 18, 2024
- October 11, 2024
- October 4, 2024
- September 27, 2024
- September 20, 2024
- September 13, 2024
- September 6, 2024
- August 30, 2024
- August 23, 2024
- August 16, 2024
- August 9, 2024
- August 2, 2024
- July 26, 2024
- July 19, 2024
- July 12, 2024