Weekly Project Updates

The Office of Planning, Design and Construction is pleased to share weekly project updates with the campus, the community, and beyond. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates and previous updates are available at the bottom of this page. If you would like additional details, or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignandConstruction@Missouristate.edu. Thank you for your interest in projects at Missouri State University.

Update for Week Ending January 11, 2019

A printable version of our Weekly Project Updates is available.

Construction of NPHC Plots

Michael Mardis, Project Manager

Meetings occurred on January 8 with a representative from the Stone Institute to discuss the current attachment system and finalize stone attachment recommendations. The consultant is working on revisions to the drawings based on these recommendations. The contractor will provide revised pricing based on the updated drawings. 

Renovation of Rooms 107 and 108, Strong Hall

Michael Mardis, Project Manager

Furniture and computers have been installed. Classroom technology components are currently being installed. The space will be ready for classes next week.

Renovation of Rooms 105 and 126, Kemper Hall

Michael Mardis, Project Manager

The submittal process will begin soon to accommodate long equipment and material lead times in order to remain on-schedule for summer construction.

Outdoor Amphitheater, West Plains Campus

Adam Shuler, Project Manager

The evaluation of bids is ongoing in coordination with all project stakeholders.

Greenhouse Addition, Temple Hall

Shanon Mitchell, Project Manager

A kick-off meeting will be scheduled for early February, with the contractor planning to mobilize in mid-February. The project is scheduled to be completed by the end of May.

Developer Led Residence Hall, Holland House

Bruce Colony, Project Manager

The first floor concrete work is in progress. The contractor is revising the project schedule to regain time lost due to weather delays. The design team has received final design comments, and the planned redesign of the courtyard will begin soon. Construction documents have been finalized for the dining hall and will be issued for review soon. A pre-application review with the City of Springfield has been submitted and review comments are due next week.

Renovation of Room 114, Meyer Library

Adam Shuler, Project Manager

Preparation of the construction schedule has begun. The kick-off meeting has been rescheduled for January 17.

Ozarks Educational Center, Bull Shoals Field Station

Adam Shuler, Project Manager

A design meeting is scheduled for January 11. Preparation of construction documents will begin in the coming weeks.

Upgrade Mechanical and Electrical Systems, Blair-Shannon House

Shanon Mitchell, Project Manager

The project was issued for bid on January 10. A pre-bid meeting is scheduled for January 17, and the bid opening is scheduled for January 24.

Phase II Renovation, Woods House

Shanon Mitchell, Project Manager

Design coordination meetings are in progress to finalize construction documents. The project is expected to be issued for bids later this month.

  • Developer Led Residence Hall, Holland House

  • Renovation of 107 and 108 at Strong Hall

Printable Version of Updates: