Update for week ending January 17, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical & electrical finish work continues on all levels. The permanent transformer
is scheduled to be on site in the upcoming weeks. The outage for installation will
not occur until Spring. Gypsum board installation and finishing continues on levels
one, two, three, and four. Preliminary and final painting continues on all levels.
Curtain wall installation and Metal & Glass Fiber Reinforced Concrete work is scheduled
to be complete by late January. Roofing work for the new addition is nearly complete.
The auditorium roof is scheduled to be complete as the curtain wall is completed.
Exterior hardscaping continues. Lab casework installation on levels three and four
continues. Cabling continues on level two and three. CRPM work has commenced. For
the existing building renovation, mechanical & electrical rough-in continues. Plumbing
and hydronic piping continues.
Autism Student Support Center, West Plains Campus
Adam Shuler, Project Manager
The project is substantially complete.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
The latest installations include cloud ceilings, ceiling tiles, carpet and vinyl base,
room signs, corner guards, concrete stair treads, stair handrails, and lighting. Miscellaneous
painting throughout the project continues. Electrical and HVAC controls work is progressing.
Block wall mortar joint repairs and staining continues. The high-performance concrete
building panel installation is on hold until the final delivery of materials is received.
Agricultural Innovation Hub, Darr Agricultural Center
Shanon Mitchell, Project Manager
This project is substantially complete, and the contractor is working on punch list
items.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Campus Construction Team has completed their work. The Job Order Contractor has submitted
final documents for the remainder of the work.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
The primary renovation work has been completed. Work is underway to convert three
unused concession stands and one racquetball court into storage space. The door frames
have arrived and are being installed. The focus in the coming days will be the installation
of the final section of drywall, mud work, and painting.
Refurbish and Renovate Main Elevator, Carrington Hall
Eric Easter, Project Manager
The elevator has been taken out of service and will be out until mid-February. The
contractors have demolished the existing components to be removed. The piping and
electrical to the new controller is complete. The new rails are being installed.
Installation of the new cab will occur when the hoist way work is complete. The controller
equipment has been installed and a large portion of the mechanical, electrical, and
plumbing has been completed.
Renovation of First and Second Floors, Kings Street Annex
Eric Easter, Project Manager
The contractor is completing punch list items as well as a few additional changes
to the project. Faculty have moved in.
Replace Roof, Hammons Hall for the Performing Arts
Eric Easter, Project Manager
The new roof has been installed. Other areas that have coatings being installed, have
been delayed due to the cold weather. This will resume when the weather is above 50
degrees. The parapet cap is being installed.
Renovate Classrooms and Hallways, Greenwood Laboratory School
Chelsea Beck, Project Manager
Work in the hallways is nearly complete. Demolition has begun on the next classroom
and observation room.
Renovation of Room 105, Meyer Library
Adam Shuler, Project Manager
Wall framing is complete, and the ceiling modifications are underway. Plumbing piping
for the new water fountain is installed. Drywall installation has begun and will continue
for a few weeks. Electrical rough-in started last week and is on-going.
Third Floor Buildout, Jordan Valley Innovation Center
Shanon Mitchell, Project Manager
The contractor plans to mobilize in February and begin work. Submittals for the project
are in progress.
Printable weekly updates
- January 17, 2025
- January 10, 2025
- December 20, 2024
- December 13, 2024
- December 6, 2024
- November 22, 2024
- November 15, 2024
- November 8, 2024
- November 1, 2024
- October 25, 2024
- October 18, 2024
- October 11, 2024
- October 4, 2024
- September 27, 2024
- September 20, 2024
- September 13, 2024
- September 6, 2024