Update for week ending May 30, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
The punch list review for the link to the new addition and the auditorium is complete.
Mechanical & electrical commissioning continues. The architectural punch list continues
as mechanical systems are not completely operational. Exterior hardscaping and site
accessories installation is nearly complete. The West Mall restoration has been delayed
by the weather. Work on the auditorium’s audio-visual has commenced. The auditorium
seating and instructor table installation is scheduled for mid-July. For the existing
building renovation, mechanical and electrical work continues. Interior wall patching
and painting have commenced. Exterior concrete patching and cleaning continues.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
The epoxy terrazzo floor installation continues. The exterior concrete panels have
been cleaned. The contractor is working through some punch list items, and some of
the work is on hold until the terrazzo floor work is complete.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
The Job Order Contractor will begin work the first week of June. The Campus Construction
Team work is complete.
Replace Roof, Hammons Hall for the Performing Arts
Eric Easter, Project Manager
The new roof has been installed. All roofs have been coated. Punch list items have
been repaired. The project is complete pending final inspection.
Renovate Classrooms and Hallways, Greenwood Laboratory School
Chelsea Beck, Project Manager
Work in the hallways is nearly complete. Work continues on the current classroom renovation.
Third Floor Buildout, Jordan Valley Innovation Center
Shanon Mitchell, Project Manager
Plumbing work for the airlines and deionized water is in progress. The Electrician
is wiring and installing conduit for lighting in the conference room. HVAC stainless
ductwork installation is nearly complete, and the phoenix valves are being installed.
Drywall tape and mud work continues.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Weather delays are occurring. The elevator pit foundation walls have been poured,
and water proofing has been installed. Excavation for new storm water and sewer lines
continues. Underslab electrical and plumbing rough-in continues. Craig Hall asbestos
abatement continues.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The new sound booth’s location has been laid out and concrete has been cut. Wall layout
continues along with electrical rough-in. Mechanical rough-in continues. The old
fire sprinkler system has been removed. They have begun demolition on the 4th floor
office spaces. The demolition has moved into the main hallway corridor. Trenches will
be filled in this week. Drywall may begin next week.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
Skylights have been ordered, and a delivery date is not yet established. The skylights
will be installed after the roof is completed. The existing roof has been removed,
and the new roof has been installed. The gravel flood coat will be installed after
the skylights are installed.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Weather delays are occurring. Footing, stem wall formwork, and rebar installation
continue throughout the building footprint. Underground chilled water piping installation
continues. New sanitary sewer line work continues.
Lighting Improvements, Plaster Stadium
Bethany Henry, Project Manager
Installation of the new wiring and infrastructure continues.
Renovate Chick-Fil-A, Plaster Student Union
Chelsea Beck, Project Manager
Wall and door framing continues. Mechanical, electrical, and plumbing rough-in continues.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The project has been awarded. A kick-off meeting will occur in early June. The Contractors
are preparing to mobilize mid-summer.
Infrastructure Support for Broadcasting, Plaster Stadium
Bethany Henry, Project Manager
A construction fence has been erected in parking lot 4. Initial demolition for new
underground conduits has begun in Parking lot 4. Demolition in the press box has begun.
Printable weekly updates
- May 30, 2025
- May 23, 2025
- May 16, 2025
- May 9, 2025
- May 2, 2025
- April 25, 2025
- April 18, 2025
- April 11, 2025
- April 4, 2025
- March 28, 2025
- March 21, 2025
- March 14, 2025
- March 7, 2025