Weekly Project Updates

Header Image for Weekly Project Updates. Shows progress photos of various construction on campus.The Office of Planning, Design and Construction is pleased to share weekly project updates with the campus, the community, and beyond. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates and previous updates are available at the bottom of this page. If you would like additional details, or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignandConstruction@Missouristate.edu. Thank you for your interest in projects at Missouri State University.

Update for Week Ending November 9, 2018

A printable version of our Weekly Project Updates is available.

Locker Room Addition, Greenwood Laboratory School

Jerry Compton, Project Manager

The project is complete.


Construction of NPHC Plots

RobRoy Viau, Project Manager

The contractor is reviewing alternative stone connection methods. A solution to the issue is expected soon. Once the solution is accepted by the consultant and the contractor, modifications will be made to the contractual documents to reflect this design revision.


Renovation of Rooms 107 and 108, Strong Hall

Michael Mardis, Project Manager

The new ceiling grid is being installed and painting will begin soon. Deliveries of the classroom technology components are arriving.The new ceiling grid, lighting, projector screen, and data wiring have been installed. Painting has commenced. New doors and hardware have been ordered and will arrive soon.


Renovation of Room 105, Kemper Hall

Michael Mardis, Project Manager

The bid opening was held on November 8. Preparation of the project budget is underway.


Outdoor Amphitheater, West Plains Campus

Adam Shuler, Project Manager

The construction documents have been advertised for bidding. Pre-bid meetings were held in early November. The bid opening has been rescheduled for November 29.


Greenhouse Addition, Temple Hall

RobRoy Viau, Project Manager

The apparent low bidder has been assisting with a cost control process to create an awardable project. The client is involved to ensure the modified budget and scope is acceptable.


Developer Led Residence Hall, Holland House

Bruce Colony, Project Manager

A deadline of mid-November has been set to finalize the design on the base building, along with a complete project estimate. Design is steadily moving towards completion for the dining hall. Meetings are being scheduled for the week prior to Thanksgiving to finalize finishes and furnishings. The scheduling consultant has begun work and an initial site visit will follow.


Renovation of Room 114, Meyer Library

Adam Shuler, Project Manager

Progress continues on the preparation of the construction documents. Cost control measures are being evaluated to ensure the project is designed within budget. The anticipated bid date for this project is in December.


Ozarks Educational Center, Bull Shoals Field Station

Adam Shuler, Project Manager

Progress continues on the preparation of the design development documents. Meetings with stakeholders are ongoing as this process continues.


Upgrade Mechanical and Electrical Systems, Blair-Shannon House

RobRoy Viau, Project Manager

The consultant is moving forward with the preparation of design development documents. These documents will be submitted for review prior to winter break.


Phase II Renovation, Woods House

RobRoy Viau, Project Manager

A meeting occurred with the consultant to begin the design process and discuss scheduling. Initial reviews will occur prior to winter break.

Hass-Darr Hall Construction Time-Lapse

  • Renovation at Hill Hall

  • Locker Room Addition at Greenwood Laboratory School

  • Renovation at Hass-Darr Hall

  • Renovation at Plaster Center for Free Enterprise

Printable Version of Updates: