Weekly Project Updates

The Office of Planning, Design and Construction is pleased to share weekly project updates with the campus, the community, and beyond. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates and previous updates are available at the bottom of this page. If you would like additional details, or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignandConstruction@Missouristate.edu. Thank you for your interest in projects at Missouri State University.

Update for Week Ending August 17, 2018

A printable version of our Weekly Project Update is available.

Renovation of Hass-Darr Hall, West Plains Campus

RobRoy Viau, Project Manager

The site concrete immediately adjacent to the facility has been installed.  The contractor is working on the curb and gutter at the street.  Final paint and finishes are being installed.  The majority of the work is ready to be reviewed.  


Renovation, Hill Hall

Michael Mardis, Project Manager

Move-in is compete and office and classroom set-up is nearly complete. Final punch list items and change orders are wrapping up this week. The contractor will be onsite for the next few weeks to make adjustments and resolve any issues.


Locker Room Addition, Greenwood Laboratory School

Jerry Compton, Project Manager

A punch list walk-thru is scheduled for August 22, at which time any remaining items to be completed will be identified. 


Mechanical Engineering Improvements, Plaster Center

Jerry Compton, Project Manager

The installation of electrical, plumbing and HVAC work is nearly complete. The installation of the ceiling grid has been completed, and the ceiling tile is being installed. Painting has been completed, and the installation of new network cabling is in progress. The installation of the floor covering is scheduled to begin during the week of August 20.


FY18 Preventative Parking Lot Maintenance

Adam Shuler, Project Manager

Work has been completed on Lots 2, 4, 11, 19, 25, 27, 29, 39, 40, 42, 47, 47B, and STMA. Work will continue on Lots 46 and 52 this week. All work is scheduled to be completed by the end of the week.  


Construction of NPHC Plots

RobRoy Viau, Project Manager

Several of the roof drains for McDonald Arena were discovered during excavation, and all of the drain repairs have been made.  The last of the footings has been poured, and the contractor is backfilling the excavation with gravel.  The concrete is currently scheduled to be poured this week.  Once the concrete has cured, steel erection will begin.


Creation of a Temporary Parking Lot, Mill Street Warehouse

Adam Shuler, Project Manager

The paving portion of the project has been complete, and the lot is ready to open. Temporary lighting and signage will be provided until permanent items are installed.

  • Renovation at Hill Hall

  • Locker Room Addition at Greenwood Laboratory School

  • Renovation at Hass-Darr Hall

  • New Wellness Center Construction

Printable Version of Updates: