Update for week ending April 18, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
The punch list review for the link to the new addition and the auditorium is scheduled
for mid-May. Mechanical & electrical commissioning continues. The architectural punch
list continues as mechanical systems are not operational. Interior door and hardware
installation is complete. Exterior soffit rework is complete. Exterior hardscaping
is nearing completion. Planting is nearing completion. Site accessories installation
has commenced. The punch list review for the building exterior and landscaping is
complete. MSU Telecommunications cabling continues on all Levels. CRPM work has commenced.
Ceiling work is complete. For the existing building renovation, mechanical and electrical
work continues. Plumbing and hydronic piping is complete. Interior wall patching has
commenced. Exterior concrete patching and cleaning continues.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
The Contractor is working through punch list items. Landscaping work is in progress.
Furniture installation has begun. Epoxy terrazzo floors have been added to the project
and the installation should begin soon.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
The Job Order Contractor has submitted their work plan for review.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
The new locker room and weight room are complete. The four new lobby storage areas
are substantially complete.
Replace Roof, Hammons Hall for the Performing Arts
Eric Easter, Project Manager
The new roof has been installed. All roofs have been coated. There are some minor
punch list items to be completed next week.
Renovate Classrooms and Hallways, Greenwood Laboratory School
Chelsea Beck, Project Manager
Work in the hallways is nearly complete. Wrapping up the current classroom renovation.
The Contractor will begin work in the next classroom next week.
Third Floor Buildout, Jordan Valley Innovation Center
Shanon Mitchell, Project Manager
Plumbing work continues above the ceiling on the 2nd floor for piping runs. Electrical
overhead lines and lighting layout are progressing. HVAC spiral ductwork installation
continues, and work on the installation for the VAV in the 2nd floor IT closet has
begun.
Turf Replacement, Plaster Stadium
Bethany Henry, Project Manager
Construction is underway. The old turf has been removed. Underlayment installation
will begin next, and new turf will be delivered.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Pier drilling is wrapping up. Concrete grade beam work will begin next week. The remaining
piers are being poured this week. The Contractor poured another small concrete mockup
wall to capture additional details, next step is wall framing. Craig Hall asbestos
abatement and demolition will begin mid-May.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The Contractor is nearing completion of the demolition of the walls and mechanical,
electrical, and plumbing. Work continues to remove the sounds booth and clear additional
abandoned piping from the ceilings.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
Skylights have been ordered, and a delivery date is not yet established. Roofing
and skylight work is to be completed simultaneously, with an anticipated start date
to occur after spring commencement.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Site excavation continues. Five feet of unsuitable soil must be removed at the building
footprint. Underground electrical work has commenced. City Utilities has set up a
temporary transformer for site power. The Contractor is preparing for underground
chilled water work to start the beginning of May.
Lighting Improvements, Plaster Stadium
Bethany Henry, Project Manager
Submittals for the project are in progress. Construction is anticipated to begin May
12.
Printable weekly updates
- April 18, 2025
- April 11, 2025
- April 4, 2025
- March 28, 2025
- March 21, 2025
- March 14, 2025
- March 7, 2025
- February 28, 2025
- February 21, 2025
- February 14, 2025
- February 7, 2025
- January 31, 2025
- January 24, 2025
- January 17, 2025