Weekly Project Updates

Weeky Project Updates

Planning, Design and Construction is pleased to share weekly project updates with the campus and community. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates and previous updates are available at the bottom of this page.

If you would like additional details or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.

Update for week ending January 16, 2026

A printable version of our Weekly Project Updates is available.

Addition & Renovation, Blunt Hall

Laura Derrick, Project Manager

For the building addition (Phase I):

Mechanical & electrical commissioning continues to be on hold due to graphics issues. A process to complete commissioning has been established. Monument signage lighting final installation is scheduled for mid-January. A short list of remaining items is being addressed and scheduled for January and February. Additional items in progress include furnishings, auditorium lighting, and miscellaneous lab equipment.

For the existing building renovation (Phase II):

  • Level 1: Mechanical and electrical are complete except for commissioning. Final lab shifts are complete. Final room finishing is underway. Door and hardware commissioning has commenced and near completion.
  • Level 2 South: Substantially complete except for lab entry painting/tackboard and card access. Door and hardware installation have commenced and near completion.
  • Level 2 North: Mechanical and electrical work near completion except for commissioning. Office and lab moves are complete or ongoing in preparation for classes. Corridors are near completion.
  • Level 3 South: Substantially complete except for lab entry painting/tackboard and card access. Door and hardware installation have commenced and near completion.
  • Level 3 North: Demolition has commenced.
  • Level 4 North: Room demolition continues. Mechanical and electrical work have commenced.
  • Roofing has commenced and is near completion.

Judith Enyeart Reynolds Complex

Michael Mardis, Project Manager

The Craig Hall addition concrete block installation is wrapping up. The Craig Hall addition roof installation continues. Craig Hall drywall finishing is wrapping up on the second floor. Craig Hall floor leveling is complete in the new student lounge. New building exterior sheathing is wrapping up while water proofing continues. New building interior framing continues. New building overhead mechanical, electrical, and plumbing rough-in continues. New building curtainwall installation has commenced, and sawtooth window framing has been installed at the south façade. New building masonry veneer is being installed on the north façade.

Phase II Renovation, Kampeter Health Sciences Hall

Eric Easter, Project Manager

The 4th floor is complete and the office furniture has been installed. Carpet installation is being completed in the first-floor lobby. Touch up painting continues in all areas. The wood wall coverings are being installed.   Demolition has begun in the 2nd and 3rd floor offices. Anticipated move in date is January 26th, with partial occupancy taking place on January 20th.

Replace Skylights, Plaster Student Union

Eric Easter, Project Manager

Drywall repairs were made over winter break. The contractor is currently working on a few punch list items. 

Clifton M. Smart III Advancement Center

Michael Mardis, Project Manager

Interior framing continues. Interior electrical, mechanical, and plumbing rough-in continue throughout the building. Roof installation is wrapping up. Curtainwall installation is 90% complete, and glass has been installed in the smaller windows along National Ave. Exterior weather barrier and liquid flashing continue around the building. The rooftop air handler installation is complete.

Replace Roof and Tuckpointing, Sunvilla Tower

Eric Easter, Project Manager

Crews have moved to the last section on the Northside and Westside of the building.  All previous work on the Northside and Westside is complete.  The contractor continues to work on real sealing the windows and construction joints on each floor. The cold weather has delayed progress.

Renovation, Cheek Hall

Adam Shuler, Project Manager

Flooring installation continues along with painting in offices. Ceilings are being installed on the Mezzanine level next week. Glass marker boards have been installed throughout phase 1 areas. Tile installation is complete in the Mezzanine level restrooms and toilet accessories have been mounted. The mezzanine wall in the lobby has been removed, and structural steel will be installed next week. The electrical conduit to the new basement panels has been installed and the switch gear will be finished next week.

Update Elevators 24, 25, & 26, Hammons House

Eric Easter, Project Manager

The elevator contractor continues to make site visits for verifications. We are currently working on reviewing submittals from the contractor. Selective demolition took place over winter break.

Renovate Suite 113, Carrington Hall

Tanya Garretson, Project Manager

Demolition is mostly complete, though some items remain to prevent disrupting the building temporarily. Dumpster delays slowed disposals but pick up is scheduled and then the space will be cleared out further. Ductwork and HVAC unit deliveries are expected this week or early next week. Two proposals for unforeseen conditions have been received with a third proposal pending. Pricing will be reviewed and rough-in work will continue.  

Drago Hall Renovation, West Plains

Shanon Mitchell, Project Manager

Concrete pour back for the plumbing and electrical work is taking place this week. Rough-in for the HVAC work has started. Submittal reviews are in progress. Anticipated project completion is at the end of the Spring 2026 semester.

Exterior Ledges Repair, Freudenberger and Blair-Shannon House

Shanon Mitchell, Project Manager

Work on the east and south elevations of Freudenberger House have started. Work will continue into the summer.

Printable weekly updates