Update for week ending December 1, 2023
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Work for the building footings and foundation walls is complete. The underfloor work
continues for the existing electrical room in the basement. The first portion of the
basement slab is complete. Level one coordination has commenced.
Autism Student Support Center, West Plains Campus
Adam Shuler, Project Manager
Site excavation continues and unforeseen conditions have been discovered below grade.
A house foundation and abandoned tank were discovered underground. The soil around
the tank is being tested for hazardous material and will be safely removed and remediated.
Sitework will continue for several weeks to deal with this issue and then concrete
formwork will be set up.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
The contractor has started mobilization and the construction staging area fence is
in place. Submittals are in progress and being reviewed. Concrete wall demolition
will start the latter half of the week, pending weather.
Agricultural Innovation Hub, Darr Agricultural Center
Shanon Mitchell, Project Manager
A pre-construction kick-off meeting was held on November 29. The contractor is working
on subcontracts and will start submittals soon. Mobilization is not anticipated until
after the first part of 2024.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Sidewalk grinding has commenced and is 20% complete.
Printable weekly updates
- December 1, 2023
- November 17, 2023
- November 10, 2023
- November 3, 2023
- October 27, 2023
- October 20, 2023
- October 13, 2023
- October 6, 2023
- September 29, 2023
- September 22, 2023
- September 15, 2023
- September 8, 2023
- September 1, 2023