Update for week ending February 21, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical & electrical finish work continues on all levels. The permanent transformer
has been delivered. The outage for installation has been postponed until warmer weather.
Gypsum board installation and finishing continues on all levels. Final painting continues
on all levels. Guardrails installation continues. Interior Glass Fiber Reinforced
Concrete work is nearing complete. Interior door/hardware installation continues.
Curtain wall installation is complete. Soffit installation has been delayed by the
weather. Roofing for the new addition and auditorium is nearly complete. Exterior
hardscaping continues while being delayed by the weather. Lab casework installation
is nearing completion. Cabling continues on all levels. CRPM work continues. Mechanical
and electrical rough-in continues. For the existing building renovation, mechanical
& electrical rough-in continues. Plumbing and hydronic piping continues. Wall patching
has begun.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
Miscellaneous work continues in preparation for the punch list walkthrough at the
end of February. Supply chain issues have delayed some product installations. Landscaping
is scheduled for early spring.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Campus Construction Team has completed their work. The Job Order Contractor has submitted
final documents for the remainder of the work. Schedule being issued.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
The primary renovation work has been completed. Work is underway to convert three
unused concession stands and one racquetball court into storage space. The initial
punch list review of the former concession stands has occurred with minor touch-ups
required. At the racquetball court, work continues at the new doorway and ramp.
Refurbish and Renovate Main Elevator, Carrington Hall
Eric Easter, Project Manager
Final inspection and a punch list review occurred last week. Elevator is operational.
There are a few punch list items to be completed.
Replace Roof, Hammons Hall for the Performing Arts
Eric Easter, Project Manager
The new roof has been installed. Other areas that have coatings being installed, have
been delayed due to the cold weather. This will resume when the weather is above 50
degrees. The parapet cap is being installed.
Renovate Classrooms and Hallways, Greenwood Laboratory School
Chelsea Beck, Project Manager
Work in the hallways is nearly complete. Ceiling work is complete. Demolition is complete
and drywall work has begun in the next classroom.
Renovation of Room 105, Meyer Library
Adam Shuler, Project Manager
Painting is underway and will be complete this week. The new wall framing, drywall,
and electrical rough-in is complete. The existing carpet has been removed, and new
carpet will be installed starting this week. The new interior storefront windows are
being installed and nearly complete.
Third Floor Buildout, Jordan Valley Innovation Center
Shanon Mitchell, Project Manager
The Contractor has begun demolition of mechanical, electrical, and plumbing items.
Material deliveries are arriving onsite, and then metal framing will begin.
Turf Replacement, Plaster Stadium
Bethany Henry, Project Manager
This project has been awarded. Submittals for the project are in progress.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
There have been delays this week due to the weather. The tunnel remains closed, and
the Grand Street crosswalk is open. The job site trailer arrived this week. Structural
scaffolding installation around the Grand Street elevator building is complete. Networking
and Telecommunications equipment is being installed in the elevator building electrical
room. The electrical to the elevator building has been completed. All utilities feeding
the Art Annex have been disconnected except electrical. Site camera installation is
complete. The concrete pour for the new sidewalk on the east side of Craig Hall is
delayed due to grading issues, options being discussed. The Art Annex demolition will
tentatively begin next week.
Printable weekly updates
- February 21, 2025
- February 14, 2025
- February 7, 2025
- January 31, 2025
- January 24, 2025
- January 17, 2025
- January 10, 2025
- December 20, 2024
- December 13, 2024
- December 6, 2024
- November 22, 2024
- November 15, 2024
- November 8, 2024
- November 1, 2024
- October 25, 2024
- October 18, 2024
- October 11, 2024
- October 4, 2024