Construction Look Ahead

Darr Construction

Below is a listing of projects that will bid over the next several months.

Grease Interceptor Upgrade, Blair-Shannon Dining Center

Project Description: The project will include removal of sanitary piping and existing grease interceptor. Contractor will install new piping as required, a new grease interceptor, and sampling port. The project will include trenching, cutting of interior concrete slab, and concrete slab repair with floor polishing to match existing floor.

Consultant:  True Engineering Group
Estimated Construction Cost:  $200,000.00

Issue for Bid:  January 17, 2023
Bid Opening:  January 31, 2023 February 9, 2023
Award of Contract:  February 17, 2023 March 15, 2023
Start of Construction: May 19, 2023

 


Addition & Renovation, Temple Hall

Project Description: Construct a 73,400 square foot science lab and office addition to Temple Hall. 

Consultant:  BNIM
Estimated Construction Cost:  $55,400,000.00

Issue for Bid:  See below
Bid Opening:  See below
Award of Contract:  Awards will be issued by the Construction Management At Risk (CMAR) firm - The Whiting-Turner Contracting Company
Start of Construction: December 19, 2022

Interested parties can find more bidding information at: https://plans.missouristate.edu/.

Packages to be Bid by Whiting-Turner (Milestone X – GMP Set):

Bid Solicitation Date: October 21, 2022

Due:  November 14, 2022 @ 4:00 pm

Packages: General Trades, Demolition; Concrete, Steel, Waterproofing, Roofing,  Fireproofing, Elevator, Earthwork & Site Utilities, Deep Foundations, and Shoring


Packages to be Bid by Whiting-Turner (Milestone B - 100% DDs)

Bid Solicitation Date: January 9th, 2023

Due:  February 1st, 2023 @ 4:00 p.m.

Packages: Lab Casework, Framing & Drywall, and Roofing


Packages to be Bid by Whiting-Turner (Milestone C – +/- 30%-50% CDs):

Bid Solicitation Date: March 10, 2023

Due:  April 3, 2023 @ 4:00 pm

Packages: Carpentry, Interior Glazing, Doors & Frames, Door Hardware, Framing & Drywall, Lab Casework, and Roofing


Packages to be Bid by Whiting-Turner (Milestone D – 100% CDs):

Bid Solicitation Date:  June 23, 2023

Due:  July 10, 2023 @ 4:00 pm

Packages: All remaining Work Packages not included in previous bidding 

 

Thank you for helping Build a Better Missouri State University.