Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending October 30, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the interior steel panel installation continues. Acoustical wood panel
preparation continues in Coger Theatre. The exterior ramp and stair concrete have
been poured, and exterior site work continues. In the new addition, wood cladding
installation continues at the south side doors. In the new building, punch list work
continues along with installation of audio-visual equipment in the Studio Theatre.
Final handrail installation continues at the main stairway.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The display case installation is nearly complete. Lobby 109 feature wall installation
continues as well as remaining punch list work.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Finishes such as flooring, paint, doors, lights and ceiling installation continue
in the offices on level 1 and in the corridors on level 2. The new hydronic and steam
piping is being installed this week and will be connected to the existing systems.
Light fixtures are being installed this week in the corridors and casework installation
is complete. The new plumbing fixtures have been installed in the restrooms, and the
water fountain will be installed on level 2 next week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 is still offline being retrofitted. Completion has been delayed until
early November. Cab finishes will be installed in early November. The project is
scheduled to be complete in January 2027.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Painting and carpet installation are ongoing.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Roof work and precast cleaning and caulking are anticipated to start in November.
The window replacement scope of the project is anticipated to start in January, pending
shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
A project kick-off meeting was held last week, and there have been multiple trade
site walks this week. The contractor has moved onsite. Exterior work will begin
next week. We are currently reviewing the schedule for the interior work, and we have
started to receive submittals for the project.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
Construction fencing is in place, with fence screening still to be installed. Lead
abatement is nearing completion, and interior demolition has begun in the new mechanical
area and locker room. The Consultants have begun receiving product submittals for
review.
Printable weekly updates
- October 30, 2026
- October 23, 2026
- October 16, 2026
- October 9, 2026
- October 2, 2026
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026
- August 14, 2026