Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending July 24, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
- Mechanical and Electrical Commissioning for Phase 1 & 1A: The final commissioning
report was discussed this week.
- Warranty items have been completed. The Consultant responded to the CMAR report.
A meeting with all parties to discuss the outcomes and project closure will occur
next week.
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4: Mechanical/Electrical are complete except for commissioning.
Corrections are ongoing. Door/hardware installation has been rescheduled for completion.
Card access installation on all floors is to be completed this week. Fume hood installation
and Pheonix are complete. Certification is scheduled for the fist week of October.
Owner required completion of offices and labs has been submitted. All spaces are
needed no later than August 7 in preparation for fall classes. Level 4 is complete.
- Exterior: Lot 18A rework is scheduled for August 3.
- Other: The replacement elevator installation is complete, and the inspection has been
rescheduled for the end of July.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall work continues throughout the work zone including the interior acoustical
wood paneling. Carpet installation at the second-floor corridor is virtually complete.
Interior painting of the addition and Coger Theatre is also near completion, this
is highlighted by the recent completion of the interior lighting. Exterior concrete
site wall formwork continues, and the sitework excavation has commenced at the northwest
corner of Craig Hall. In the new building, drywall installation, finishing and painting
continue at the first floor. Installation of the exterior metal soffit panel and the
maroon metal cladding continues. Carrington Avenue sidewalk work continues, and the
Grand Street crosswalk remains open.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Construction activities continue to progress across multiple areas of the project
at a very consistent pace. Exterior terra cotta cladding installation is ongoing along
the south elevation of the Event Center and is nearing completion. Interior finishes
continue to advance. The second-floor office spaces are in the final phase of finish.
An architectural punch occurred in the event space this week. Installation of Phenix
marble, wood ceilings in the main corridor, wood wall panels at the north stair, and
terrazzo flooring continue throughout the facility. Final site improvements continue,
with continued construction of Parking Lot 27 and site retaining walls surrounding
the Event Lawn.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The new chilled water piping has been installed in the basement mechanical room and
will be tested next week. The new heat exchanger is being moved to the basement this
week and will be installed next week. Wall framing is nearly complete on level 1,
and drywall installation and MEP rough-in is underway. Structural steel installation
in the level 2 mechanical room for slab openings is complete. The new air handler
units will be brought into the building through a second-floor window over the next
week. This will require a crane and the west entrance to the building will be closed
periodically. MEP rough-in on level 2 is nearly complete and ceiling grid installation
is underway.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Chilled water lines are being insulated, and the fan coil unit startup is next week.
Electrical work in the hoist way was completed during shutdown. Access panels are
being installed for the fire alarm installation. Additional electrical work continues
in the penthouse and telecommunications. The elevator continues to be modernized,
and an elevator inspection will take place in early August. The anticipated completion
of elevator 24 is August 10.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor is finalizing the project work and will start testing and balancing
the system starting July 25. A punchlist walkthrough is planned on July 30.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed the work on the
roof and 4th floor and will work their way around the building utilizing smaller lifts.
The work is anticipated to be complete by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Staff members have moved out of the office and the removal process for surplus items
is ongoing. Abatement is scheduled to begin July 27 with construction work to follow
on August 17.
Printable weekly updates
- July 24, 2026
- July 17, 2026
- July 10, 2026
- July 3, 2026
- June 26, 2026
- June 19, 2026
- June 12, 2026
- June 5, 2026
- May 29, 2026
- May 22, 2026
- May 15, 2026