Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending August 28, 2026
A printable version of our Weekly Project Updates is available.
Building Renovation, Blunt Hall
Laura Derrick, Project Manager
- Levels 1, 2, 3, and 4: Mechanical/Electrical are complete. A final commissioning schedule
continues to be determined. Issues with programming persist as reporting is provided.
All offices, labs and support spaces are complete except for one storage area being
utilized by construction. Punchlist items are near full completion.
- Exterior: Lot 18A rework is near completion.
- Other: Irrigation system corrections are near completion.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the interior acoustical wood panel installation in Coger Theatre continues.
Terrazzo floor polishing continues. The exterior concrete ribbon wall installation
continues throughout the site. The sidewalk has been poured between the new building
and Craig Hall, and the ramp grading at Craig Hall is underway. Casework installation
in the new building is nearly complete, and audio-visual installation continues in
the Black Box Theatre. The new sprung dance floor installation continues on the second
floor, and the main exterior metal cladding installation is complete, awaiting final
closure pieces. Interior wood panel installation continues, and the performance classroom
mirror installation has commenced. Storefront and glass have been installed at the
second-floor classrooms, and concrete slab polishing has commenced.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds. The contractor has been making repairs
for reported items identified in recent weeks.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The maroon exterior terracotta cladding installation is nearing completion at the
south elevation. Wood wall panel installation continues in Traditions Hall. Glass
railing and handrail installation are nearly complete. Final terrazzo grind and polishing
is nearly complete. The lobby, Room 109 feature wall installation continues, and
the carpet installation is nearing completion in the Event Center. The Ursa Major
light fixture has been installed, and the bear head light fixture in the Bears Den
is being installed. First-floor and second-floor office desk and cubicle installation
continues. Exterior wood soffit panel installation is complete. Topsoil is now in
place at the Event Lawn and irrigation installation continues at the East Lawn.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Wall framing and drywall installation continues on level 1, and MEP rough-in is underway.
New mechanical units have been installed on level 2, and ductwork is being adjusted
to fit the layout. MEP rough-in on level 2 is ongoing, and ceiling grid installation
is complete. Fire alarm updates were completed last week, and the entire building
is now using the new fire alarm panel. The new lighted department signs have been
installed in the lobby.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 will be taken offline this week, and the contractor will be back on-site
next week to begin demolition. The staging area in the parking lot will be recaptured
this week.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed work on the roof
and 4th floor and will work their way around the building utilizing smaller lifts. They
are currently working on the third-floor areas. The work is anticipated to be complete
by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Electrical work continues. Coordination meetings are ongoing with Networking and
Telecommunications regarding data and technology. Construction progress meetings
began this week.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
The General Contractor is working on submittals and a logistics schedule for the building.
Roof work and precast cleaning and caulking are anticipated to start in October.
The window replacement scope of the project is anticipated to start in December, pending
shipment of materials.
Printable weekly updates
- August 28, 2026
- August 21, 2026
- August 14, 2026
- August 7, 2026
- July 31, 2026
- July 24, 2026
- July 17, 2026
- July 10, 2026
- July 3, 2026
- June 26, 2026
- June 19, 2026
- June 12, 2026