Weekly Project Updates

Weeky Project Updates

Planning, Design and Construction is pleased to share weekly project updates with the campus and community. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates, and previous updates are available at the bottom of this page.

If you would like additional details or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.

Update for week ending September 25, 2026

A printable version of our Weekly Project Updates is available.

Judith Enyeart Reynolds Complex

Michael Mardis, Project Manager

In Craig Hall, the terrazzo floor polishing is nearly complete and interior steel panel installation continues.  The exterior ramp, stair and site work continues.  In the new building, wood cladding is complete on the west side, and the large double door frame installation has commenced.

Phase II Renovation, Kampeter Health Sciences Hall

Eric Easter, Project Manager

The project is substantially complete.  We are pursuing some additional upgrades to the facility with remaining contingency funds.  The contractor has been making repairs for reported items identified in recent weeks.

Clifton M. Smart III Advancement Center

Michael Mardis, Project Manager

Wood wall panel installation continues in Traditions Hall.  The Lobby 109 feature wall installation continues.  Installation of the bear head light fixture continues in the Bears Den.  Installation of the stone surround at the fireplace is complete.  Landscaping installation is complete.  Stainless steel planter installation continues at the south end of the site.

Renovation, Cheek Hall

Adam Shuler, Project Manager

The hydronic pipe and heat exchanger installation in the basement mechanical room is nearly complete. The new automatic transfer switch and associated electrical equipment will be installed this week. Wall framing and drywall on level 1 is complete, and ceiling grid installation is ongoing. MEP rough-in on level 1 is nearing completion, and floor boxes have been installed. Carpet and ceilings have been installed in classrooms and labs on level 2, and plumbing installation for the level 2 restrooms continues this week.

Update Elevators 24, 25, & 26, Hammons House

Eric Easter, Project Manager

Elevator 25 has been taken offline.  Demolition and replacement of the elevator continue.  Additional disconnects will need to be added per code requirements.  This elevator is anticipated to be completed in October.

Correct Water Infiltration, Strong Hall

Eric Easter, Project Manager

The Contractor continues work on Strong Hall.  They have completed the work on the roof, fourth and third floors.  They are now working on the second and ground floors.  Work is anticipated to be complete by October.

Renovate Rooms 422 & 424, Carrington Hall 

Tanya Garretson, Project Manager

Data installation and painting are underway.

Exterior Renovation, Glass Hall 

Shanon Mitchell, Project Manager

Submittals are in progress for the project. Roof work and precast cleaning and caulking are anticipated to start in October. The window replacement scope of the project is anticipated to start in December, pending shipment of materials. 

Install Cooling Tower & Process Piping, JVIC Building 6

Eric Easter, Project Manager

The project kick-off meeting is scheduled to occur in early October.  Discussions are occurring with the Contractor and the client regarding coordination for the project.  Equipment is being procured.

Renovation for Football Locker Room, McDonald Arena

Danielle Palmer, Project Manager

The project kick-off meeting was held on September 23.  The Contractor is developing the construction schedule and finalizing site logistics.  Construction and staging are anticipated to begin in mid-October.  Lead abatement began this week, and containment barriers will remain in place throughout the abatement process.

Printable weekly updates