Update for week ending April 2, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is on track for completion. The final visit
with the Commissioning Agent is scheduled for next week. Final furnishings will be
installed by mid-May. A warranty review was held this week. A preliminary list of
warranty items has been submitted by the consultants for review and is scheduled for
completion mid-May.
For the existing building renovation (Phase II):
- Level 1, 2, 3 (South), and 4 (North): Mechanical/Electrical work is complete except
for commissioning. The Commissioning Agent will be on site next week to commence work.
Door/hardware is still pending due to door delays. Card access to follow.
- Level 3 North: Mechanical/Electrical work is near completion. Room finishes and ceiling
grid installation continues. Completion is scheduled for late April with room moves
scheduled for the first two weeks of May.
- Level 4 South: Mechanical/Electrical work has commenced. Completion is scheduled for
early June with room moves scheduled for mid-June.
- Atrium: Scaffolding has been removed and replaced at the South window wall to complete
sealing of glass gaps and is scheduled to be removed next week.
- Roofing: South side roofing has commenced and is near completion. Work is scheduled
to be completed at the end of April.
- Exterior: Landscaping is scheduled to commence in May. Briggs Street final asphalt
topping is scheduled for early June. Completion of the building cleaning is scheduled
for late April or early May.
- Additional work: The replacement elevator is scheduled to commence early to mid-May.
Fume Hood installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
The Craig Hall interior concrete ramp and walls have been poured. The Craig Hall drywall
installation and finishing are wrapping up in the new student lounge, restrooms, and
Box Office. The new building drywall installation continues throughout the building.
The new building mechanical, electrical, and plumbing rough-in continues. Masonry
veneer installation continues at the scene shop addition. Exterior soffit sheathing
installation continues. Underground conduit has been installed for the new transformer.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
First floor punch list items are being completed. A punch list review for the 3rd
floor was conducted last week. The contractor is working on completing those punch
list items. The 2nd floor punch list review will occur mid-April. The contractor
will be reseeding the laydown area this week.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing are wrapping up at the Event Hall and continues
throughout the second floor offices. Interior electrical, mechanical, and plumbing
rough-in continues throughout the building. Elevator installation continues. Exterior
terracotta cladding installation continues at the east façade. Exterior insulation
continues at the south façade. Window trim/flashing installation is wrapping up at
the east façade. The trash enclosure and the golf cart storage building foundation
work continues. The southeast landscape wall has been poured outside the executive
board room.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
Work on the building exterior is complete. The roofing portion of the work continues.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Phase 2 began with demolition work on Level 2. A fully enclosed trash chute has been
installed on the NW corner of the building to safely remove demolished materials from
Level 2. Abatement work on Level 2 will be complete this week and they will start
on Level 1 next week. On the Mezzanine Level, HVAC testing and balancing is finishing
up. Furniture installation in the lobby and common areas is now complete.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make periodic site visits for verifications.
Submittal reviews continue. The contractor plans to move onsite mid-May.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
Above ceiling inspections have occurred with a few items to address. Coordination
discussions are ongoing for the fan coil unit test/start up and the fire alarm test.
The ceiling grid edge trim installation is ongoing. Painting and floor installation
is occurring this week. Activities scheduled for next week are the installation of
ceiling runners, ceiling tile, grilles, registers, diffusers, and lighting.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Painting and wall panel installation will be complete this week. Flooring installation
is scheduled for next week. Project completion is anticipated for mid-May.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting continues on the west wing courtyard
side and east wing east side of Freudenberger House. The Contractor continues work
at Blair-Shannon House on the south and west elevations. The work will continue into
Summer 2026.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The project construction kick-off meeting was held this week. Submittal reviews are
in progress; work is anticipated to begin mid-May. The anticipated project completion
is mid-July.
Printable weekly updates
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026