Update for week ending May 8, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is on track for completion. The final Commissioning
Report has been issued and deficiencies are being addressed. Final furnishings will
be installed by mid-June. A warranty review was held. A preliminary list of warranty
items has been submitted by the consultants for review and is scheduled for completion
mid-May.
For the existing building renovation (Phase II):
- Level 1, 2, 3 (South), and 4 (North): Mechanical/Electrical work is complete except
for commissioning. The Commissioning Agent was onsite last week, with corrections
ongoing. Door/hardware and card access are nearly complete.
- Level 3 North: the architectural punch list review occurred on May 4th. Mechanical/Electrical
work is complete except for controls. Room moves are scheduled for the first two weeks
of May.
- Level 4 South: Mechanical/Electrical work continues. Completion is scheduled for early
June with room moves scheduled for mid-June.
- Atrium: The pit has been substantially cleared to begin carpeting.
- Roofing: scheduled to be completed by the first of June (weather pending).
- Exterior: Landscaping is scheduled to commence in May. Briggs Street final asphalt
topping is scheduled for early June.
- Additional work: The replacement elevator is scheduled to commence next week. Fume
Hood installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Mechanical, electrical, and plumbing installation continues in the scene shop addition.
Terrazzo installation continues. Lobby light fixture installation continues. A/V installation
in Room 206 has commenced. Painting continues throughout the second floor. Excavation
for the new Craig Hall exterior ramp has commenced. New building drywall installation
and finishing continues on the first floor. New building interior painting continues
at the 2nd floor. New building mechanical, electrical, and plumbing is wrapping up.
New building exterior soffit panel sub structure is wrapping up. New building ceiling
grid installation continues at the 2nd floor. The dumpster/electrical courtyard concrete
walls are complete. The contractors are preparing to install the new transformers
for permanent power.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The 2nd floor punch list review has been completed. The Contractor is working on correcting
deficient items.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Acoustical ceiling grid installation is wrapping up on the second floor. Drywall installation
and finishing continue at the first-floor main corridor. Painting continues at the
first-floor offices. Network cabling installation continues at the second floor. Exterior
terracotta cladding installation continues at the north, east, and west facades. Interior
terracotta installation continues. The golf cart storage enclosure masonry is wrapping
up.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
This project is substantially complete. The contractor is preparing costs for awning
repairs.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Work is limited this week for finals and commencement. Demolition on level 1 continues
with overhead mechanical, electrical, and plumbing and walls being removed this week.
Demolition work on level 2 is complete and new wall framing is underway. Drywall,
ductwork, and door frames are being installed on level 2 this week and mechanical
room demolition has begun.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make periodic site visits for verifications.
A kickoff meeting was held this week. Submittal reviews continue. The contractor plans
to move on site next week.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
This project is substantially complete, and the department moved into the space this
week. Remaining punch list items will be addressed.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Cabinets and countertop installation is in progress. HVAC, plumbing, and electrical
finish work continues. Owner furnished equipment is being installed. The punch list
review is scheduled for May 13th.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting are in progress on the west wing west
side and north side of Freudenberger House. The Contractor continues to work at Blair
House on the southeast side, and the north side of Shannon House. The work will continue
into Summer 2026.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
Submittal reviews are in progress. Work is anticipated to begin mid-May. The anticipated
project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor plans to mobilize in June.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
This project has been awarded, and work is scheduled to begin next week.
Printable weekly updates
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026