Update for week ending April 19, 2024
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
The level four concrete pour is complete. The level five (roof) concrete pour is scheduled
for the end of April. Level five shoring continues. Mechanical & electrical work continues
on level zero, level one and level two. Interior metal stud framing continues on level
zero, level one and level two. Exterior metal stud framing continues. Topping out
is scheduled for May 22.
Autism Student Support Center, West Plains Campus
Adam Shuler, Project Manager
The concrete floor slab and other concrete work is complete. The structural steel
installation continues, all columns have been installed, and roof trusses are being
installed this week. Steel installation will continue for the next several weeks.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
The first of three level 1 concrete slab pours is in place. The second slab pour is
scheduled for this week. Underground electrical conduit and basement electrical equipment
work continues.
Agricultural Innovation Hub, Darr Agricultural Center
Shanon Mitchell, Project Manager
Foundation and footing work continues. Under slab electrical and plumbing work has
begun.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Sidewalk replacement to commence the week after graduation in May.
MSU Baseball Training Facility
Adam Shuler, Project Manager
The electrical and plumbing rough-in is complete. The stud wall framing, and masonry
work is complete. Drywall installation started this week and will continue next week
followed by painting.
Turf Replacement, Allison South Stadium
Eric Easter, Project Manager
Submittals have been reviewed and approved. The contractor is securing materials for
the project. Work will commence after graduation in May.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
Concrete has been poured, and masonry has been installed in all required areas at
the new locker room space. HVAC installation, electrical work, drywall installation,
and the removal of the bleachers in the north and south gyms is ongoing. Further work
in the north and south gyms, and the east and west decks will begin following graduation
in May.
Roof Replacement, Garst Dining Center
Eric Easter, Project Manager
Project submittals are being reviewed. The contractor is securing all of the materials
for the project. Work will commence after graduation in May.
Printable weekly updates
- April 19, 2024
- April 12, 2024
- April 5, 2024
- March 29, 2024
- March 22, 2024
- March 15, 2024
- March 8, 2024
- March 1, 2024
- February 23, 2024
- February 16, 2024
- February 9, 2024
- February 2, 2024
- January 26, 2024
- January 19, 2024
- January 12, 2024