Update for week ending May 1, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is on track for completion. The final Commissioning
Report has been issued and deficiencies are being addressed. Final furnishings will
be installed by mid-May. A warranty review was held. A preliminary list of warranty
items has been submitted by the consultants for review and is scheduled for completion
mid-May.
For the existing building renovation (Phase II):
- Level 1, 2, 3 (South), and 4 (North): Mechanical/Electrical work is complete except
for commissioning. The Commissioning Agent was onsite last week, with corrections
ongoing. Door/hardware is complete. Card access is near completion.
- Level 3 North: the punch list review was postponed to May 4. Mechanical/Electrical
work is complete except for controls. Room finishes are complete. Final cleaning has
commenced. Completion is scheduled for late April with room moves scheduled for the
first two weeks of May.
- Level 4 South: Mechanical/Electrical work continues. Completion is scheduled for early
June with room moves scheduled for mid-June.
- Atrium: The pit has been substantially cleared to begin carpeting.
- Roofing: scheduled to be completed by the first of June (weather pending).
- Exterior: Landscaping is scheduled to commence in May. Briggs Street final asphalt
topping is scheduled for June.
- Additional work: The replacement elevator is scheduled to commence mid-May. Fume Hood
installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Craig Hall painting is wrapping up in the new student lounge, restrooms, and Box Office.
Wall tile and ceiling grid has been installed in the new restrooms. Mechanical, electrical,
and plumbing installation continues in the scene shop addition. Terrazzo installation
continues. The new building drywall installation and finishing continue throughout.
The new building interior painting continues on the 2nd floor. The new building mechanical,
electrical, and plumbing are wrapping up. The new building exterior soffit panel sub
structure is being installed. The new building remaining glass unit installation continues.
The new building ceiling grid installation continues on the 2nd floor. The dumpster/electrical
courtyard concrete walls continue.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
Punch list items are being completed. A punch list review for the second floor will
occur next week.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The hard lid ceiling work has commenced at the north stairs. The remaining exterior
glass installation is wrapping up. Painting continues on the 2nd floor. Acoustical
ceiling grid installation continues on the second-floor offices. Drywall installation
and finishing continue throughout the building. Projectors and screens have been hung
in the Event Hall. Interior mechanical, electrical, and plumbing rough-in is wrapping
up throughout the building. Electrical finishes are being installed in the second-floor
offices. The exterior terracotta cladding installation continues at the north, south,
east, and west facades. Interior terracotta cladding installation has commenced. Exterior
insulation is wrapping up at the Event Hall. Jobsite trailers have been removed.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
This project is substantially complete. There will be additional repairs to the awning.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Demolition work on level 2 is almost complete and new wall framing has begun. Ductwork
and door frames are being installed on level 2 this week and mechanical room demolition
will begin next week. Demolition on level 1 continues with overhead mechanical, electrical,
and plumbing and walls being removed this week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make periodic site visits for verifications.
A kickoff meeting was held this week. Submittal reviews continue. The contractor plans
to move onsite mid-May.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
The punch list review occurred this week and the department move-in is scheduled for
next week. The contractor is working on punch list items, to include replacing the
breakroom flooring.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
HVAC, plumbing, and electrical finish work are in progress. Fire alarm has been installed
and tested. Cabinets and countertops will be installed next week. A punch list review
is scheduled for May 7.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting are in progress on the west wing west
side and north side of Freudenberger House. The Contractor continues work at Blair
House on the north side, and the west side of Shannon House. The work will continue
into Summer 2026.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
Submittal reviews are in progress. Work is anticipated to begin mid-May. The anticipated
project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor plans to mobilize in June.
Printable weekly updates
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026