Update for week ending September 12, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical and electrical commissioning is complete except for two items which will
be completed in the next two weeks. Final furnishings installation continues. Furniture
installation for the graduate student office is to be completed in September. Interior
building signage has been removed due to fabrication issues. The monument sign installation
is complete. The dedication of the new addition will occur on September 12. For the
existing building renovation, Level 2 & 3 South are substantially complete except
for office ceilings and corridors. Mechanical & electrical continues on Level 2 North
and Level 1. Air handling units start-up and commissioning has commenced. Wall patching
and painting have commenced on Level 2 North and Level 1. Phase 2B (Levels 2 & 4 North
and Level 1) are scheduled to be completed in December.
Third Floor Buildout, Jordan Valley Innovation Center
Shanon Mitchell, Project Manager
The punch list review is taking place this week, and substantial completion will be
issued.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Steel erection continues. Craig Hall addition concrete wall formwork is being installed.
Craig Hall underslab mechanical, electrical, and plumbing rough-in continues. Framing
is complete in the second floor acting studio and costume storage area.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The exterior windows are being installed. Electrical/conduit work is complete. Work
is in progress with the lighting fixtures. Ceiling dry fall is complete. Painting
is progressing on the first floor. The cable trays are installed. The fourth floor
walls are being painted. The drop ceiling is being installed. Store fronts have been
installed.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
All skylights have been installed, the demoed material will be removed this week,
and the completion of the roof will take place next week.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Steel erection will continue through mid-September. Exterior wall framing for the
event center is starting next week. Mockup concrete foundation work is complete.
Lighting Improvements, Plaster Stadium
Bethany Henry, Project Manager
The field lights are operational, and training has been completed. Minor adjustments
to the egress fixtures are currently in progress.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The Contractor has installed the swing stage, and has begun the resealing of the window.
Infrastructure Support for Broadcasting, Plaster Stadium
Bethany Henry, Project Manager
Final termination of wiring infrastructure is in process. Punch list items are being
corrected.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The basement selective demolition for the new electrical room has been completed.
The remaining abatement of flooring materials was completed this week. Saw cutting
slab and plumbing rough-in will begin on the first floor at the end of this week.
Mezzanine framing and overhead mechanical, electrical, and plumbing rough-in will
be completed in the coming weeks.
Printable weekly updates
- September 12, 2025
- September 5, 2025
- August 29, 2025
- August 22, 2025
- August 15, 2025
- August 8, 2025
- August 1, 2025
- July 25, 2025
- July 18, 2025
- July 11, 2025
- July 3, 2025
- June 27, 2025
- June 20, 2025
- June 13, 2025
- June 6, 2025