Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending July 17, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
- Mechanical and Electrical Commissioning for Phase 1 & 1A: The Commissioning Agent
was on site this week. Final report is pending.
- Warranty items have been completed. The Consultant has responded to the CMAR report.
Meetings are occurring with all parties to discuss outcomes and project closure is
expected next week.
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4: Mechanical/Electrical are complete except for commissioning.
Corrections are ongoing. Door/hardware installation has been rescheduled for completion
at the end of next week. Card access installation on all floors is complete except
for the remaining doors to be installed. Fume hood installation and Pheonix are complete.
Certification is pending. Owner required completion of offices and labs has been
submitted. All spaces are needed no later than August 7 in preparation for fall classes.
- Exterior: Landscaping and irrigation are complete. The Briggs Street final asphalt
topping is complete. Lot 18A rework is expected to occur next week.
- Other: The replacement elevator installation is complete, and the inspection has been
rescheduled for the end of July.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the elevator installation is complete, awaiting inspection. The lobby
light fixture installation is complete, and the interior acoustical wood paneling
continues. Carpet installation at the second-floor corridor is near completion.
Interior painting of the addition and Coger Theatre is also near completion. Exterior
concrete site wall formwork continues and the sitework excavation has commenced at
the northwest corner of Craig Hall. In the new building, drywall installation, finishing
and painting continue at the first floor. Installation of the exterior metal soffit
panel and metal cladding continues. Carrington Avenue sidewalk work continues, and
the Grand Street crosswalk remains open.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Exterior terracotta cladding installation continues at the south face of the Event
Center. Interior Phenix marble installation continues. Wood ceiling installation
continues at the main corridor, and the wood wall panel installation has commenced
at the north stair. Terrazzo installation continues throughout the building. Wall
tile installation is complete at the first-floor restrooms. Restroom accessory installation
continues at the second floor. Lot 27 parking lot work continues. Site wall work
continues around the Event Lawn.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Wall framing continues on level 1, and drywall installation is also underway. Structural
steel is being installed in the level 2 mechanical room. MEP rough-in on level 2 is
nearly complete and paint priming is underway. Power has been reactivated on level
3 this week and the electrical closet will be complete in coming weeks. The re-route
of the generator conduit is complete, and the fiber lines have been re-routed to the
new data center room.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Chilled water lines are being insulated, and the fan coil unit startup is next week.
Electrical work in the hoist way was completed during shutdown. Access panels are
being installed for the fire alarm installation. Additional electrical work continues
in the penthouse and telecommunications. The elevator continues to be modernized,
and an elevator inspection will take place in early August. The anticipated completion
of elevator 24 is August 10.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor will be finalizing the project work during the next two weeks. A punchlist
walkthrough is planned on July 30.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed the work on the
roof and 4th floor and will work their way around the building utilizing smaller lifts.
The work is anticipated to be complete by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Notices to proceed have been issued for construction and abatement work. Staff members
are scheduled to move out of this area next week with abatement scheduled to begin
the last week of July. Construction work is scheduled to begin mid-August.
Printable weekly updates
- July 17, 2026
- July 10, 2026
- July 3, 2026
- June 26, 2026
- June 19, 2026
- June 12, 2026
- June 5, 2026
- May 29, 2026
- May 22, 2026
- May 15, 2026
- May 8, 2026