Update for week ending June 19, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
- Mechanical and Electrical Commissioning for Phase 1 & 1A: Final commissioning items
were discussed this week.
- Warranty items have been completed. Items will be reviewed next week for compliance.
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4: Mechanical/Electrical are complete except for commissioning.
Corrections are ongoing. Door/hardware near completion. Card Access on fourth floor
is ongoing. Fume hood installation is nearing completion.
- Level 4 (South): Mechanical/Electrical punch list walk through is complete.
- Atrium: New domes are pending completion.
- Roofing: The schedule has been delayed to mid-June due to weather.
- Exterior: Landscaping has commenced. The Briggs Street final asphalt topping is scheduled
for mid-July.
- Other: The replacement elevator installation has commenced, and the inspection has
been scheduled for early July.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Mechanical, electrical, and plumbing installation is nearing completion in the scene
shop addition. In Craig Hall, interior storefront and glass has been installed at
the student lounge. Elevator installation continues. Terrazzo installation is complete
and polishing remains. Lobby light fixture installation continues. Second floor
door and hardware installation continues. Existing wood acoustical panel demolition
in Coger Theatre continues. On the exterior, concrete site wall formwork installation
for the new exterior ramp continues. Excavation and grading along Grand Street continues.
New building drywall installation and finishing continue on the first floor. Elevator
installation is complete. Ceiling tile, electrical and audio/visual fixtures are
being installed. Phenix marble cladding installation continues at the south façade
as well as the interior lobby.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The Contractor is working on completing punch list items. We are pursuing some additional
upgrades to the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing is nearing completion on the first floor. Network
cabling installation is nearing completion. Exterior terracotta cladding installation
continues at the Event Center. Interior terracotta installation continues. Phenix
marble installation continues on the east façade. Terrazzo installation is complete
on the second floor, and polishing remains. Painting continues throughout the first
floor. Second floor office storefront glass installation is nearing completion.
Wood ceiling installation continues on the second floor conference room. The Event
Center air handling unit is operational. Acoustical wood wall panel installation
continues in the Event Center. Lot 27 underground utility work continues. Excavation
and underground storm water piping installation has commenced at the Event Lawn.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The project is substantially complete. We have added additional upgrades to the awning
and work will begin next week.
Renovation, Cheek Hall
Adam Shuler, Project Manager
An intermediate slab (abandoned concrete roof deck) was discovered between level 1
and level 2, and it is being removed. Wall framing continues on level 1 along with
MEP rough-in, and drywall installation has begun on level 1. Drywall installation
on level 2 is nearing completion and MEP rough-in is nearly complete. This includes
overhead ductwork, VAV box installation, mechanical piping, and electrical work. Power
has been turned off on level 3, and a new electrical closet is being constructed.
There will be a building wide cooling outage on June 23 to tie in the new hydronic
piping.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The new fan coil unit is being prepared for installation. Electrical and elevator
work continues.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The Contractor is working on punch list items. This project is substantially complete.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
The project is substantially complete.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor is working on ductwork installation, new lighting, control wiring,
ceiling drywall and painting. New roof curbs and roof top HVAC units were installed
last week. Anticipated project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on the west side of Strong Hall. The work is anticipated
to be complete in October.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
Lots 21 and 44 are substantially complete. Lot 35 will be partially closed starting
Sunday, June 21 at 5 PM. These parking spots will reopen the following day as work
is completed. Bear Park South is currently being cleaned and is scheduled for new
striping early next week. Bear Park North is scheduled to be closed June 24 through
July 3 for cleaning, restriping, and safety painting. All work is weather-dependent,
and schedules may change. Please do not move, walk, or drive around barricades, cones,
or other traffic safety equipment. Please refer to the Administrative Services Notifications Blog for more information on closures.
Printable weekly updates
- June 19, 2026
- June 12, 2026
- June 5, 2026
- May 29, 2026
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026