Update for week ending July 10, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
-
Mechanical and Electrical Commissioning for Phase 1 & 1A: Remaining items are ready
for final testing by the commissioning agent.
-
Warranty items have been completed. A report on the remaining items has been circulated
and is now under review.
For the existing building renovation (Phase II):
-
Level 1, 2, 3, and 4: Mechanical/Electrical are complete except for commissioning.
Corrections are ongoing. Door/hardware installation has been rescheduled for completion
next week. Card access installation on all floors is complete except for the remaining
doors to be installed. Fume hood installation and Pheonix are complete. Owner required
completion of offices and labs has been submitted. All spaces are needed no later
than August 7 in preparation for fall classes.
- Exterior: Landscaping and irrigation are complete. The Briggs Street final asphalt
topping is scheduled for next week.
-
Other: The replacement elevator installation is complete, and the inspection has been
rescheduled for the end of July.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, elevator installation is complete, awaiting inspection. The lobby light
fixture installation continues. Interior acoustical wood paneling installation continues.
Carpet installation in the student lounge is complete. In the Craig Hall addition,
interior painting continues. For the exterior, concrete site wall formwork continues.
In the new building, drywall installation, finishing and painting continue at the
first floor. Ceiling tile, electrical and A/V fixtures installation is wrapping up
at the second floor. Exterior metal soffit panel installation continues. Exterior
metal cladding installation has commenced. Carrington Avenue underground storm water
work is complete. Carrington Avenue sidewalk work has commenced. The Grand Street
crosswalk is open.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
We are pursuing some additional upgrades to the facility with remaining contingency
funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Exterior terracotta cladding installation continues at the south face of the Event
Center. Interior terracotta installation is complete. Phenix marble installation is
complete. Painting continues throughout the first floor. Carpet installation is complete
at the second floor offices. Wood ceiling installation continues at the main corridor.
Terrazzo installation continues throughout the building. Wall tile installation continues
in the first floor restrooms. Acoustical wood wall panel installation is complete
at the Event Center. Lot 27 parking lot work continues. Site wall formwork continues
around the Event Lawn.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The re-route of the generator conduit is complete, and the fiber lines running from
Cheek Hall to the Burgess House have been re-routed to the new data center room. Wall
framing is nearly complete on level 1, and drywall installation continues this week.
Drywall installation and mechanical, electrical, and plumbing rough-in on level 2
is complete and painting has begun this week. A new electrical closet is being constructed
on level 3 and power is expected to be back on next week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The chilled water lines are being insulated, and the fan coil unit startup is next
week. Electrical work in the hoist way was completed during the shutdown. Additional
electrical work continues in the penthouse. The elevator continues to be modernized.
The anticipated completion of Elevator 24 is mid-August.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor is wrapping up the major portion of their work and will have the kitchen
and dining area open for a camp this weekend. They will finalize project work over
the next two weeks in-between weekend camps.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed work on the roof
and 4th floor and will work their way around the building utilizing smaller lifts.
It is anticipated that work will be completed by October.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
Lots 21, 35, and 44 are substantially complete, as are Bear Park South and North.
Minor corrections are needed before the project is complete. All work is weather-dependent,
and schedules may change. Please do not move, walk, or drive around barricades, cones,
or other traffic safety equipment. Please refer to the Administrative Services Notifications Blog for more information on closures.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Notices to proceed were issued on June 26 for construction and abatement work. Staff
are scheduled to move out of this area the week of July 20 with abatement scheduled
to begin at the end of July. Construction work is scheduled to begin mid-August.
Printable weekly updates
- July 10, 2026
- July 3, 2026
- June 26, 2026
- June 19, 2026
- June 12, 2026
- June 5, 2026
- May 29, 2026
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026