Update for week ending July 3, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
-
Mechanical and Electrical Commissioning for Phase 1 & 1A: Remaining items are ready
for final testing by the commissioning agent.
-
Warranty items have been completed. A report on remaining items has been issued with
a response requested by the end of this week.
For the existing building renovation (Phase II):
-
Level 1, 2, 3, and 4: Mechanical/Electrical are complete except for commissioning.
Corrections are ongoing. Door/hardware installation has been rescheduled for completion
next week. Card access installation on all floors is complete except for the remaining
doors to be installed. Fume hood installation is complete and Pheonix near completion.
Owner required completion of offices and labs has been submitted. All spaces are
needed no later than August 7 in preparation for fall classes.
-
Roofing: Complete.
-
Exterior: Landscaping to be complete next week. The Briggs Street final asphalt topping
is scheduled for mid-July.
-
Other: The replacement elevator installation is complete, and the inspection has been
scheduled for early July.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, elevator installation is near completion. Installation of the lobby
light fixture and the interior acoustical wood paneling continues. Exterior concrete
site wall formwork continues, and the sidewalk has been poured along Grand Street.
New building drywall installation, finishing and painting continues on the first floor.
Ceiling tile, electrical and audio-visual fixtures installation is nearing completion
on the second floor. Phenix marble cladding installation is complete and grouting
continues. Exterior metal soffit panel installation continues. The Carrington Avenue
stormwater work has commenced. The Grand Streed pedestrian underpass is closing,
and the crosswalk will be in place next week.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
We are pursuing some additional upgrades to the facility with remaining contingency
funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Installation of the exterior terracotta cladding continues in the Event Center. Interior
terracotta installation is nearing completion. Phenix marble installation is nearing
completion at the east façade. Painting continues throughout the first floor. Second
floor office storefront glass installation is complete, and wood doors have been installed
at the second-floor offices. Cabinets have been installed in the second-floor workroom
and carpet installation continues at the second-floor offices. Installation of the
wood ceiling continues at the main corridor. Terrazzo stair treads have been installed,
and terrazzo installation continues throughout the building. Wall tile installation
continues in the first-floor restrooms. Acoustical wood wall panel installation is
nearing completion in the Event Center. Lot 27 work continues and site walls foundation
work continues around the Event Lawn.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The project is substantially complete.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The re-route of the generator conduit is being completed this week from level 1 to
the basement. Fiber and copper lines running from Cheek Hall to the Burgess House
are being re-routed to the new data center room. Wall framing is nearly complete on
level 1, and drywall installation has begun. Drywall installation on level 2 is complete
and MEP rough-in is wrapping up. Power has been turned off on level 3, and a new electrical
closet is being constructed.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
A new chilled water line has been installed to the new fan coil unit and installation
of the unit continues. The elevator shut down is complete. New conduits have been
installed in the hoistway, and elevator installation continues.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The Contractor is working on punch list items. This project is substantially complete.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
The project is substantially complete.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor is working on ductwork installation, new lighting, control wiring,
and painting. Anticipated project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. It is anticipated that work will be
completed by October.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
Lots 21, 35, and 44 are substantially complete, as are Bear Park South and Bear Park
North. Only minor corrections are needed before the project is complete. All work
is weather-dependent, and schedules may change. Please do not move, walk, or drive
around barricades, cones, or other traffic safety equipment. Please refer to the
Administrative Services Notifications Blog for more information on closures.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Notices to proceed were issued on June 26 for construction and abatement work. Staff
are scheduled to move out of this area the week of July 20 with abatement scheduled
to begin at the end of July. Construction work is scheduled to begin mid-August.
Printable weekly updates
- July 3, 2026
- June 26, 2026
- June 19, 2026
- June 12, 2026
- June 5, 2026
- May 29, 2026
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026