Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending October 2, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, interior steel panel installation continues. The exterior ramp, stair
and site work continues. In the new building, large double doors have been installed.
Punch list work continues, and the audio-visual equipment installation continues in
the Studio Theatre.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Wood wall panel installation is nearly complete in Traditions Hall, and installation
of the display case has commenced. Lobby 109 feature wall installation continues,
and cabinet installation is nearly complete in the Bears Den. First and second floor
reception desks have been installed, and punch list work continues. Stainless steel
planter installation is nearly complete at the south end of the site.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The hydronic pipe and heat exchanger installation in the basement mechanical room
is complete. There will be a power outage this weekend to install an automatic transfer
switch and associated electrical equipment. Wall framing and drywall on level 1 is
complete, and ceiling grid installation is ongoing. Casework installation has begun
on both level 1 and level 2. Carpet and ceilings have been installed in classrooms
and labs on level 2. Sheetrock and wall base are being installed in level 2 restrooms
this week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 has been taken offline. Demolition and replacement of the elevator continue.
The new AHU is completed. A valve was replaced due to lack of capacity. This elevator
is anticipated to be completed in late October.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They will be finishing on the south
side of the building this week, along with a few other touch-up areas. Then they
will begin working on the north side of the building.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Delivery of new ceiling tile is anticipated soon, with installation to follow thereafter.
Wall repair is ongoing, and painting will continue through mid-October.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Submittals are in progress for the project. Roof work and precast cleaning and caulking
are anticipated to start in October. The window replacement scope of the project is
anticipated to start in December, pending shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
The project kick-off meeting is scheduled to occur in early October. Discussions
are occurring with the Contractor and the client regarding coordination for the project.
Equipment is being procured.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
Construction staging and fencing will begin mid-October. A temporary ramp at the front
entrance has been installed in preparation for construction inside. Lead abatement
is ongoing.
Printable weekly updates
- October 2, 2026
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026
- August 14, 2026
- August 7, 2026
- July 31, 2026
- July 24, 2026
- July 17, 2026