Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending August 21, 2026
A printable version of our Weekly Project Updates is available.
Building Renovation, Blunt Hall
Laura Derrick, Project Manager
- Level 1, 2, 3, and 4: Mechanical/Electrical are complete. Final commissioning schedule
will be determined this week.
- Existing fume hood installation and controls are complete and functioning.
- All offices, labs and support spaces are complete except for one storage area being
utilized by construction.
- Punchlist items are nearly complete, and work related to occupancy of rooms was completed
prior to the start of classes.
- Exterior: Lot 18A rework continues.
- Other: Irrigation system corrections are near completion.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall the interior acoustical wood panel installation continues in Coger Theatre.
Terrazzo floor polishing continues. Exterior landscaping installation continues at
the west side of the new building. Paver installation is complete on the west side
of the new building and sidewalk formwork installation is nearly complete between
the new building and Craig Hall. Casework installation continues throughout the new
building. Final wall painting continues on the second floor and audio-visual installation
continues in the Black Box Theatre. Installation of the new sprung floor has commenced
on the second floor, and the main exterior metal cladding installation is complete,
awaiting final closure pieces.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The maroon exterior terracotta cladding installation is nearing completion at the
south elevation. Wood wall panel installation continues in Traditions Hall. Glass
railing and handrail installation continues. Final terrazzo grind and polishing remain
to be completed. The feature wall installation has commenced in the lobby, Room 109.
Carpet installation continues in the Event Center and carpet installation in the Executive
Board Room and Bears Den is nearly complete. Commercial appliances have been installed
in the catering kitchen. First and second floor office desk and cubicle installation
has commenced. Exterior wood soffit panel installation continues, as well as grading
for the new sidewalk and ramps located on the south side of the building.
Renovation, Cheek Hall
Adam Shuler, Project Manager
New wayfinding signage in phase 1 areas was installed last week. Wall framing and
drywall installation is nearly complete on level 1, and MEP rough-in is underway.
The air handler units have been installed in the level 2 mechanical room, and ductwork
is being adjusted to fit the layout. MEP rough-in on level 2 is ongoing, and ceiling
grid installation is complete. Fire alarm updates for the entire building will be
completed this week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator has passed inspection and is in use. The cab finishes are to be installed
next week. Elevator 25 will also be taken offline next week.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed work on the roof
and 4th floor and will work their way around the building utilizing smaller lifts. The
work is anticipated to be complete by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Construction began this week, and electrical work is ongoing.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Construction began this week, and electrical work is ongoing.
Printable weekly updates
- August 21, 2026
- August 14, 2026
- August 7, 2026
- July 31, 2026
- July 24, 2026
- July 17, 2026
- July 10, 2026
- July 3, 2026
- June 26, 2026
- June 19, 2026
- June 12, 2026