Update for week ending May 15, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning remaining items are to be addressed next week.
Final trend reports will be issued the following week for approval. Final furnishings
will be installed by mid-June. A preliminary list of warranty items has been submitted
by the consultants for review and is scheduled for completion this month.
For the existing building renovation (Phase II):
- Level 1, 2, 3 (South), and 4 (North): Mechanical/Electrical work is complete except
for commissioning. The Commissioning Agent was onsite last week, with corrections
ongoing. Door/hardware and card access are nearly complete.
- Level 3 North: The punch list walk through items have been issued. Mechanical/Electrical
work is complete except for controls. Room moves are in progress.
- Level 4 South: Mechanical/Electrical work continues. Completion is scheduled for early
June with room moves scheduled for mid-June.
- Atrium: The pit has been substantially cleared to begin carpeting. Work is scheduled
to commence in early June.
- Roofing: Scheduled to be completed by the first of June (weather pending).
- Exterior: Landscaping is scheduled to commence in June. Briggs Street final asphalt
topping is scheduled for early June.
- Additional work: The replacement elevator is scheduled to commence next week. Fume
Hood installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Mechanical, electrical, and plumbing installation continues in the scene shop addition.
Terrazzo installation continues. Lobby light fixture installation continues. A/V installation
in Room 206 continues. Painting continues throughout the second floor. Excavation
for the new Craig Hall exterior ramp continues. The concrete site walls formwork continues.
Sidewalk removal along Grand Street continues. The new building’s drywall installation
and finishing continue at the first floor. The new building interior painting continues
at the second floor. The new building ceiling grid installation continues at the second
floor. Preparing to install the new transformers for permanent power.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The contractor is working on completing punch list items. Additional upgrades to the
facility will occur with project contingency.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing continue at the first-floor main corridor. Network
cabling installation continues at the second floor. Exterior terracotta cladding installation
continues at the Event Hall. Interior terracotta installation continues. Second floor
office storefront installation has commenced. Concrete site wall formwork installation
continues at the north and south sides of the building. Golf cart storage masonry
and steel is complete, awaiting roof and garage door.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
This project is substantially complete. Costs for the awning repairs are being evaluated.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Demolition of walls and overhead mechanical, electrical, and plumbing is complete
on level 1, and floor and ceiling removal has begun in the corridor next to the restroom.
Demolition of restrooms on level 2 is underway and will be complete next week. Drywall,
ductwork, and door frames are being installed on level 2 and mechanical, electrical,
and plumbing rough-in has begun. There was an electrical shut-down this week to accommodate
the connection of new electrical panels.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Contractors moved onsite this week. Power was shut down and a new panel was installed.
Contractors continue to work on electrical items. The elevator replacement will occur
later in June.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The punch list review was performed this week, and substantial completion has been
achieve.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting continues on the west wing west side
and north side of Freudenberger House. The Contractor continues to work at Blair House
on the southeast side, and the north side of Shannon House. The work will continue
into Summer 2026.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
Submittal reviews are in progress. Work is anticipated to begin next week. The anticipated
project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor plans to mobilize in June.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
Construction has begun on Lot #44 with the removal of portions of the asphalt surface.
Construction on Lots #21 and #35 will begin next week. The first phase is estimated
to take two weeks, weather permitting. A second phase of sealing and striping will
be performed later in June.
Printable weekly updates
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026