Update for week ending March 6, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & electrical commissioning is scheduled to be complete this week. The Commissioning
Agent is scheduling a final visit. Additional furnishings are scheduled for delivery
next week and through mid-April. A warranty review was held this week and items to
be resolved are in progress.
For the existing building renovation (Phase II):
- Level 1: Mechanical/Electrical work is complete except for commissioning. Door/hardware
is scheduled to be complete in one week with card access to follow.
- Level 2: Card access installation is near completion. Door/hardware is near completion.
Mechanical/Electrical work is complete except for commissioning.
- Level 3 South: Card access installation commenced this week. Ongoing due to balance
of door installation delays. Door/hardware installation is scheduled to be completed
next week.
- Level 3 North: Mechanical/Electrical work and room finishes continue.
- Level 4 North: The punch list review is complete. Mechanical/Electrical work is near
completion. Finish painting & ceilings are complete in rooms, except for the corridor
which is pending. Lab & critical office moves have been completed. Other moves are
scheduled in the coming weeks.
- Level 4 South: Work has begun.
- Roofing on the south side has commenced.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Craig Hall interior ramp work continues as well as terrazzo installation. Craig Hall
painting continues on the second floor. The new building drywall installation continues.
The new building mechanical, electrical, and plumbing rough-in continues. The new
building masonry veneer installation continues at the north façade. The new building
exterior soffit framing continues. Awaiting the remaining exterior glass units.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The first and fourth floors are complete. There is punch-list work occurring on the
first floor. There are wall coverings that need to be installed due to a manufacturer’s
error. The wall coverings will be delivered in early March. The air handling unit
installation is complete, pending a test and balance. Drywall work has begun on the
new 2nd and 3rd floor offices.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
A final walk through will occur next week.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Interior framing continues along the main first floor corridor and offices. Drywall
work continues throughout the Event Hall and at the second-floor offices. The Event
Hall acoustical ceiling panel installation is complete. Interior electrical, mechanical,
and plumbing rough-in continue throughout the building. Awaiting remaining exterior
glass units for installation. Exterior terracotta cladding sub framing installation
continues around the building.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
Work on the exterior is complete. The roofing portion of the work started this week.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Ceiling and floor installation is ongoing in the lobby and common areas. Furniture
installation will be complete next week in the Mathematics and Computer Science faculty
offices. Fire alarm devices and networking jacks are being installed this week. Casework
in the break rooms, copy rooms, conference rooms, and common areas are being installed
this week. Framing and drywall for the Mezzanine corridor to the elevator is nearly
complete.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make periodic site visits for verifications.
Submittal reviews continue.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
The contractor is installing control valves to the hydronic piping, plumbing for the
breakroom sink and refrigerator, and installing the fire suppression devices and wiring.
They are continuing electrical work and running condensate piping. The walls have
been primed throughout, and the floor defect has been repaired. Coordination with
JCI is ongoing in preparation for the suite pressure test.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Door frames and drywall installations are in progress. Project completion is anticipated
for mid-May.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work on the west wing courtyard side and east wing east
side of Freudenberger House is in progress. The contractor will be proceeding with
the painting portion of their work as temperatures allow. The contractor has mobilized
and is to begin work on the south elevation of Blair-Shannon House. The work will
continue into Summer 2026.
Printable weekly updates
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026
- December 19, 2025
- December 12, 2025
- December 5, 2025