Update for week ending June 5, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
- Mechanical & Electrical Commissioning for Phase 1 & 1A: Consistent issues persist.
Three items remain on the punch list, as well as completing deliverables.
- Pit furniture installation is scheduled for next week.
- Warranty items have been completed.
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4 (North): Mechanical/Electrical are complete except for commissioning.
Corrections are ongoing. Door/hardware near completion. Card Access on fourth floor
is ongoing.
- Level 4 South: The punch list walk through is complete. Mechanical/Electrical punch
list walk through is scheduled for mid-June.
- Atrium: Pit carpet and base are complete. The bookshelf refresh is complete. New dome
lighting and domes are pending completion.
- Roofing: The schedule has been delayed to mid-June due to weather.
- Exterior: Landscaping is to commence next week. The Briggs Street final asphalt topping
is scheduled for mid-July.
- Other: The replacement elevator installation has commenced, and the inspection has
been scheduled for early July. Fume Hood installation has commenced. Fourth floor
is complete and is being connected to services.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Mechanical, electrical, and plumbing installation continues in the scene shop addition.
Terrazzo installation is complete and polishing remains. Roller shade installation
continues in the Student Lounge. Light fixture installation in the lobby continues.
Painting continues throughout the second floor. Scaffolding installation is nearly
complete in Coger Theatre for fire restoration work. Plumbing fixtures installation
has commenced in the new restrooms. The concrete site wall is being formed for the
new exterior ramp. Storm water piping installation continues along Grand Street.
New building drywall installation and finishing continues on the first floor. New
building interior painting continues on the second floor. New building ceiling grid
installation is nearing completion on the second floor. New building Phenix marble
cladding installation continues at the south and west façades.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The Contractor is working on completing punch list items. We are pursuing some additional
upgrades to the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing are nearly complete. Network cabling installation
continues on the first floor. Exterior terracotta cladding installation continues
at the Event Hall. Interior terracotta installation continues. Phenix marble installation
continues at the east façade. Terrazzo installation is complete on the second floor
and polishing remains. Second floor office storefront glass installation continues.
The fireplace has been installed. Wood ceiling installation commenced at the south
second floor conference room. Roof installation on the golf cart storage building
is nearly complete. Lot 27 underground utility work continues.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The project is substantially complete. We have added additional upgrades to the awning.
Color selection to match the existing awning, and fabrication will begin soon.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Demolition of piping in the basement mechanical rooms will continue for several weeks.
Wall framing and MEP rough-in has started on level 1. Framing and MEP rough-in on
level 2 is complete and wall insulation is being installed. Intermediate slab removal
and structural framing will start next week. Drywall installation on level 2 will
continue for the next few weeks. Power has been turned off on level 3, and a new electrical
closet is being constructed.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The new beam is installed, and the elevator has now been taken offline. The next
crane pick is scheduled for the middle of next week. Electrical and fire alarm work
continues.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The Contractor is working on punch list items. This project is substantially complete.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
The Contractor is completing patching and painting on the last sections of Blair House
and Shannon House with an anticipated completion within the next two weeks.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
Demolition work is complete. The Contractor is installing new ductwork and new electrical
for the new HVAC units. Anticipated project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor will be onsite next week.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
Carrington Circle Drive work is complete and the concrete is curing. This portion
of the project is set to be completed this week. Lots 21, 35 and 44 asphalt repairs
have been completed, and the parking surface has been resealed. New parking line
striping has commenced. All lots will be open after striping is complete and has
cured. Remaining work includes installation of new concrete wheel stops, new ADA
signs and other miscellaneous items. Work may require portions of the lots to be
closed in the future. Bear Park North is tentatively scheduled to be closed June
17 through June 26 for cleaning, restriping and safety painting. Bear Park South
is tentatively scheduled to be closed June 24 through July 3 for cleaning, restriping
and safety painting. Please do not move or drive around barricades at lot entrances.
Refer to the Administrative Services Notifications Blog for more information on closures.
Printable weekly updates
- June 5, 2026
- May 29, 2026
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026