Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending November 20, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the interior steel panel installation continues. Acoustical wood panel
preparation continues in Coger Theatre. The exterior ramp and stair concrete have
been poured, and exterior site work continues. Remaining punch list items in the
new building continue to be addressed.
Renovation, Cheek Hall
Adam Shuler, Project Manager
A new trash enclosure and service drive are being constructed between Cheek Hall and
Wells House. The area will remain closed for the next few weeks while work is being
completed. All new HVAC systems are operational for phase 2, and controls are being
adjusted to accommodate. The new wayfinding and room signs are being installed in
phase 2 areas in the coming weeks. The new level 2 restrooms are nearing completion,
and final finishes are being installed in other phase 2 areas.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 is still offline, being retrofitted. Completion has been delayed until
late November. Cab finishes will be installed after the elevator has been retrofitted.
The project is scheduled to be completed in January 2027.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
The project is substantially complete, and staff moved in on November 18. Remaining
punch list items will continue to be addressed.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Roof work and precast cleaning and caulking are in progress. The window replacement
scope of the project is anticipated to start in February, pending shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
The Contractor has mobilized on-site and begun sitework in preparation for the installation
of underground utilities. There has been a slight delay in the boring process, but
the Contractor finished boring this week. Due to the delay in boring, the Contractor
will be moving to interior work next week. We continue to receive submittals for
the project, and they are being reviewed by the project team.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
Interior demolition continues in the renovation areas. Product submittals continue
to be submitted and are being reviewed by the design consultants and campus team.
Electrical infrastructure upgrades along Kings Ave. are scheduled to begin next week.
Printable weekly updates
-
-
- November 20, 2026
- November 13, 2026
- November 6, 2026
- October 30, 2026
- October 23, 2026
- October 16, 2026
- October 9, 2026
- October 2, 2026
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026