Update for week ending December 12, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical and electrical commissioning continues to be on hold due to graphics issues.
The process to complete commissioning has been established but no dates have been
confirmed yet. Final Link furnishings installation is complete. Monument signage
lighting final installation is pending. A short list of items remain and are currently
being addressed and scheduled. Remaining project items are forecasted to be complete
by the end of December except for additional items to be funded by remaining project
budget.
For the existing building renovation (Phase II):
Level 1 mechanical/electrical work is nearly complete. Level 1 lab shifts are complete.
The next shift is scheduled for next week. Level 1 door/hardware has commenced and
is ongoing. Level 2 South is substantially complete except for lab entry painting
and tackboard. Level 2 South door/hardware installation commenced and is ongoing.
Level 2 North mechanical/electrical work is near completion. Level 2 North office
moves have commenced. Lab moves are scheduled for next week. Level 2 North corridors
are near completion. Level 3 South is substantially complete except for lab entry
painting, tackboard and doors/hardware. Level 3 North demolition is scheduled to
commence next week. Level 4 North room demolition continues. Level 4 North mechanical/electrical
work has commenced. Roofing work commenced this week.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
The Craig Hall addition concrete block installation continues. The Craig Hall interior
MEP rough-in is wrapping up. Exterior framing and sheathing continue around the perimeter
of the new building. Overhead mechanical, electrical and plumbing rough-in continues
in the new building. The second-floor interior framing continues in the new building.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The 4th floor is complete. Ceramic tile and LVT is complete. Floor prep is complete.
Carpet is being installed. Glass doors have been installed. The contractor continues
to touch up paint on all areas. The Fry Reglet’s have been installed, and they are
working on installing the wall coverings. They have started demo on the 3rd floor
offices.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
All Skylight and roof work had been completed. We are coordinating the schedule to
make the drywall repairs over winter break.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The exterior framing is wrapping up, and sheathing installation continues throughout
building. Interior framing continues. Drywall installation in the Event Center continues.
Interior electrical, mechanical and plumbing rough-in continues throughout building.
Roof installation continues at the eastern side of the building. Curtainwall installation
is wrapping up at the north and south entry and west along the event lawn. Exterior
weather barrier and liquid flashing installation continue around building.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The crews have moved to the last section on the North side and West side. All previous
work on the North and West is completed. They continue to work on resealing the windows
and construction joints on each floor, recent rain has slowed their progress on these
sides.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The ceiling grid and light fixture installation on the mezzanine level is on-going.
Wall framing for the basement electrical room was completed this week. The overhead
piping, HVAC, and in-wall piping installation continues on Level 1. Drywall finishing
and painting is nearly complete on the mezzanine level and is underway on Level 1.
Shoring and demolition for the lobby area will begin next week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make site visits for verifications. We are
currently working on reviewing submittals from the contractor. Selective demolition
will take place over winter break to determine if concrete masonry unit walls will
need reinforcing for installation of new hoist beam.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
Mechanical, electrical, and ductwork demolition are underway and will continue through
the end of the year. Rough-in has started in selective areas.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The project construction kick-off meeting was held on December 4th. The contractor
is scheduled to mobilize and begin demo of walls and floors starting the week of December
8th and then proceed with demo of plumbing and electrical. Submittal reviews are in
progress. Anticipated project completion is the end of the Spring 2026 semester.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
The project construction kick-off meeting was held on December 3rd. The contractor
is scheduled to mobilize the week of December 22nd. The project will continue into
summer 2026.
Printable weekly updates
- December 12, 2025
- December 5, 2025
- November 21, 2025
- November 14, 2025
- November 7, 2025
- October 31, 2025
- October 24, 2025
- October 17, 2025
- October 10, 2025
- October 3, 2025
- September 26, 2025
- September 19, 2025