Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending October 23, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the interior steel panel installation continues. Acoustical wood panel
preparation continues in Coger Theatre. The exterior ramp and stair concrete have
been poured, and exterior site work continues. In the new addition, wood cladding
installation continues at the south side doors. In the new building, punch list work
continues along with installation of audio-visual equipment in the Studio Theatre.
Final handrail installation continues at the main stairway.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The display case installation is nearly complete. Lobby 109 feature wall installation
continues as well as remaining punch list work.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The new hydronic and steam piping has been installed and connected to the existing
systems. Carpet, doors, and ceiling grid installation continues on level 1. Flooring
and ceilings have been installed in classrooms and labs on level 2. Plumbing fixtures
and tile were installed in level 2 restrooms last week. Light fixtures are being installed
this week in the corridors, and casework installation is complete.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 is still offline, being retrofitted. This is expected to be completed
in late October. Cab finishes will be installed in early November.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
This project is now substantially complete.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Painting and carpet installation are ongoing. Data plates are currently being installed.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Submittals are in progress for the project. Roof work, precast cleaning and caulking
are anticipated to start in late October or early November. The window replacement
scope of the project is anticipated to start in January, pending shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
The project kickoff meeting was held this week. The Contractor will move onsite next
week to begin exterior work. The project team is currently reviewing an anticipated
schedule for the interior work to begin.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
Construction fencing installation for the staging area is nearly complete. Lead abatement
is ongoing but also nearing completion. Demolition is beginning in the new locker
room area.
Printable weekly updates
- October 23, 2026
- October 16, 2026
- October 9, 2026
- October 2, 2026
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026
- August 14, 2026
- August 7, 2026