Update for week ending May 22, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is nearly complete. Office furniture installation
is complete. Pit furniture is pending carpet installation. A preliminary list of warranty
items has been submitted by the consultants for review and is scheduled for completion
this month.
For the existing building renovation (Phase II):
- Level 1, 2, 3 (South), and 4 (North): Mechanical/Electrical work is complete except
for commissioning. The Commissioning Agent has been onsite, with corrections ongoing.
Door/hardware and card access are nearly complete.
- Level 3 North: The punch list walk through items have been issued. Mechanical/Electrical
work is complete except for controls. Room moves are in progress.
- Level 4 South: Mechanical/Electrical work continues. Completion is scheduled for early
June with room moves scheduled for mid-June.
- Atrium: Carpeting is scheduled to commence in early June.
- Roofing: Scheduled to be completed by the first of June (weather pending).
- Exterior: Landscaping is scheduled to commence in June. Briggs Street final asphalt
topping is scheduled for early June.
- Additional work: The replacement elevator is scheduled to be completed early July.
Fume Hood installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Mechanical, electrical, and plumbing installation continue in the scene shop addition.
Terrazzo installation continues. Roller shade installation has commenced in the Student
Lounge. Lobby light fixture installation continues. Painting continues throughout
the second floor. Excavation for the new Craig Hall exterior ramp continues. Concrete
site walls formwork continues. Storm water piping has been installed along Grand Street.
The new building drywall installation and finishing continues at the first floor.
The new building interior painting continues at the second floor. The new building
ceiling grid installation continues at the second floor. The new building Phenix marble
cladding installation has commenced at the west façade. Transformers have been installed,
awaiting City Utilities to delivery meter for permanent power.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The contractor is working on completing punch list items. Additional upgrades to the
facility will occur with project contingency.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing are 85% complete throughout the building. Network
cabling installation continues at the first floor. Exterior terracotta cladding installation
continues at the Event Hall. Interior terracotta installation continues. Phenix marble
installation has commenced at the east façade. Terrazzo installation has commenced
on the second floor. Second floor office storefront installation is complete. Concrete
site wall formwork installation continues at the north and south sides of the building.
Awaiting roof and garage door for the golf cart storage building.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
This project is substantially complete. Awning repairs are being scheduled.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Demolition of mechanical pipe in the basement is underway. Demolition is nearing completion
on level 1 and wall framing has begun. Door frames and hydronic pipe installation
will start soon on level 1. Demolition of restrooms on level 2 is complete. Drywall,
ductwork, and door frames installation on level 2 is nearing completion and MEP rough-in
has begun.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Demolition is underway, and Contractors are prepping for the installation of the new
beam and column. The first crane pick will be next week to bring up new steel and
other supplies.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The Contractor is working on punch list items. This project is substantially complete.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting continues on the west wing west side
and north side of Freudenberger House. The Contractor continues to work at Blair House
on the southeast side, and the north side of Shannon House. The work will continue
into Summer 2026.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor has mobilized and started demolition work. Anticipated project completion
is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor plans to mobilize in June.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
All construction is still on schedule. The current weather forecast for next week
could potentially cause delays.
-
Carrington Circle Drive - Existing concrete drive and a portion of the sidewalk have
been removed. A new base layer of rock has been installed. Steel reinforcement will
be set next week after the holiday, and concrete pouring will be determined by the
weather.
-
Lot #21 - Work began today to remove portions of the existing asphalt. A new rock
base and asphalt repair will follow.
-
Lot #35 - As divisions of work are completed on Lot #21, those crews will then shift
to Lot #35.
-
Lot #44 - Asphalt repairs have been completed and need to be fully cured before allowing
traffic. The contractor is finishing the new concrete curb and gutter along the perimeter.
Please do not move or drive around barricades at lot entrances. Refer to the Campus
Closure Notifications for when impacted areas will be opened/closed.
Printable weekly updates
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026