Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending October 16, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, interior steel panel installation continues. In Coger Theatre, acoustical
wood panel preparation continues. The exterior ramp, stair and site work continues.
In the new addition, wood cladding preparation at the south elevation continues.
In the new building, punch list work continues along with installation of the audio-visual
equipment in the Studio Theatre.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The display case installation is nearly complete. Lobby 109 feature wall installation
continues as well as remaining punch list work.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The cooling shutdown that occurred last week was successful to connect the new hydronic
piping. Carpet, doors, and ceiling grid installation has begun on level 1. Flooring
and ceilings have been installed in classrooms and labs on level 2. Sheetrock and
wall base were installed in level 2 restrooms last week. Casework installation is
complete on both level 1 and level 2.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 is still offline, being retrofitted. New motors, cabling and controllers
have been installed. The Contractor is coordinating efforts to complete this elevator
by the end of October.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor is complete on all sides but has touch-up work to be completed on the
north side. This work is dependent on weather. Anticipated completion is for the
end of October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Ceiling tile installation is complete, and the walls have been prepared for painting.
Painting is underway and is scheduled to be complete by October 18. Carpet installation
is to begin next week, while Telecom installs the final data connections and cover
plates.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Submittals are in progress for the project. Roof work and precast cleaning and caulking
are anticipated to start in October. The window replacement scope of the project is
anticipated to start in late December, pending shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
The project kickoff meeting is scheduled for next week. Equipment procurement is complete,
and coordination with the contractor is underway to finalize the project schedule.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
Installation of construction fencing will begin this week north of McDonald Arena,
and the Kings Street pedestrian walkway will be closed. Please refer to the closure notice for additional details. Lead abatement is ongoing.
Printable weekly updates
- October 16, 2026
- October 9, 2026
- October 2, 2026
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026
- August 14, 2026
- August 7, 2026
- July 31, 2026