Weekly Project Updates

Header

Planning, Design and Construction is pleased to share weekly project updates with the campus and community. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates and previous updates are available at the bottom of this page.

If you would like additional details or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@Missouristate.edu. Thank you for your interest in projects at Missouri State University.

Update for week ending April 19, 2024

A printable version of our Weekly Project Updates is available.

Addition & Renovation, Blunt Hall

Laura Derrick, Project Manager

The level four concrete pour is complete. The level five (roof) concrete pour is scheduled for the end of April. Level five shoring continues. Mechanical & electrical work continues on level zero, level one and level two. Interior metal stud framing continues on level zero, level one and level two. Exterior metal stud framing continues. Topping out is scheduled for May 22.

Autism Student Support Center, West Plains Campus

Adam Shuler, Project Manager

The concrete floor slab and other concrete work is complete. The structural steel installation continues, all columns have been installed, and roof trusses are being installed this week. Steel installation will continue for the next several weeks.

Addition & Renovation, Kemper Hall

Shanon Mitchell, Project Manager

The first of three level 1 concrete slab pours is in place. The second slab pour is scheduled for this week. Underground electrical conduit and basement electrical equipment work continues.

Agricultural Innovation Hub, Darr Agricultural Center

Shanon Mitchell, Project Manager

Foundation and footing work continues. Under slab electrical and plumbing work has begun.

Sidewalk Improvements, Springfield Campus

Laura Derrick, Project Manager

Sidewalk replacement to commence the week after graduation in May.

MSU Baseball Training Facility

Adam Shuler, Project Manager

The electrical and plumbing rough-in is complete. The stud wall framing, and masonry work is complete. Drywall installation started this week and will continue next week followed by painting.

Turf Replacement, Allison South Stadium

Eric Easter, Project Manager

Submittals have been reviewed and approved. The contractor is securing materials for the project. Work will commence after graduation in May.

Renovate Locker Room, Hammons Student Center

Tanya Garretson, Project Manager

Concrete has been poured, and masonry has been installed in all required areas at the new locker room space. HVAC installation, electrical work, drywall installation, and the removal of the bleachers in the north and south gyms is ongoing. Further work in the north and south gyms, and the east and west decks will begin following graduation in May.

Roof Replacement, Garst Dining Center

Eric Easter, Project Manager

Project submittals are being reviewed. The contractor is securing all of the materials for the project. Work will commence after graduation in May.

Printable weekly updates