Update for week ending May 29, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is nearly complete. Pit furniture is pending
carpet installation. A final warranty review is scheduled for next week.
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4 (North): Mechanical/Electrical work is complete except for commissioning.
The Commissioning Agent has been onsite, with corrections ongoing. Door/hardware is
nearly complete.
- Level 4 South: A punch list walk through is scheduled for next week.
- Atrium: Carpeting is scheduled to commence in early June.
- Roofing: Scheduled to be completed by the first of June (weather pending).
- Exterior: Landscaping is scheduled to commence in June. Briggs Street final asphalt
topping is scheduled for early July.
- Additional work: The replacement elevator installation has commenced and is scheduled
for completion early July. Fume Hood installation is scheduled for early June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Mechanical, electrical, and plumbing installation continue in the scene shop addition.
Terrazzo installation continues. Roller shade installation continues in the Student
Lounge. Light fixture installation in the lobby continues. Painting continues throughout
the second floor. Door and hardware installation continues at the second floor. Concrete
site walls formwork and pouring continue. Concrete removal continues along Grand Street.
New building drywall installation and finishing continues at the first floor. New
building interior painting continues at the second floor. New building ceiling grid
installation is wrapping up on the second floor. New building Phenix marble cladding
installation continues at the south and west facades.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The contractor is working on completing punch list items. Additional upgrades to the
facility will occur with project contingency.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing are 85% complete throughout the building. Network
cabling installation continues at the first floor. Exterior terracotta cladding installation
continues at the Event Hall. Interior terracotta installation continues. Phenix marble
installation has commenced at the east façade. Terrazzo installation continues on
the second floor. Second floor office ceiling tile installation continues. First floor
ceiling grid installation is wrapping up. Concrete site wall formwork installation
continues at the south side of the building. The roof has been installed at the golf
cart storage building. Underground electrical work has begun in Lot 27.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
This project is substantially complete. Awning repairs are being scheduled.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Demolition of the mechanical pipe in the basement will continue for several weeks.
Demolition is completed on level 1 and wall framing has begun. Door frames and hydronic
pipe installation will start soon on level 1. Door frames installation on level 2
is complete and mechanical, electrical, and plumbing rough-in has begun. Drywall installation
on level 2 will continue for the next few weeks. Fire alarm device installation is
completed on level 3 and will continue in the non-renovation areas of the building.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Contractors continue demolition work. A crane was onsite this week. Contractors are
installing the new beam and column. Electrical demolition continues as well as preparations
for the elevator removal.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The Contractor is working on punch list items. This project is substantially complete.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work, and painting continues on the west wing west side
and north side of Freudenberger House. The Contractor continues to work at Blair House
on the southeast side, and the north side of Shannon House. The work will continue
into Summer 2026.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor has mobilized and started demolition work. Anticipated project completion
is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor plans to mobilize in June.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
Parking lot maintenance is underway. The current weather forecast could potentially
cause delays. Please do not move or drive around barricades at lot entrances. Refer
to the Administrative Services Notification Blog for when impacted areas will be opened/closed.
Printable weekly updates
- May 29, 2026
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 2, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026