Update for week ending February 6, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & electrical commissioning has resumed as the graphics issues have been
resolved. Final testing is scheduled for mid-February. Final installation for the
monument signage lighting is scheduled for mid-February. Additional items in progress
include furnishings, auditorium lighting, and miscellaneous lab equipment. Delivery
dates are scheduled throughout February and March.
For the existing building renovation (Phase II):
- Level 1: Mechanical/Electrical are complete except for commissioning. The first air
handling unit has been tested and is complete. All other units are to follow the same
testing. Final room finishing is scheduled for completion in two weeks. Door/hardware
is scheduled to be completed in the coming weeks.
- Level 2: Card access installation is near completion and ready for testing. Door/hardware
is near completion. Mechanical/Electrical work is complete except for commissioning.
- Level 3 South: Card access installation commenced this week. Door/hardware installation
is near completion.
- Level 3 North: Demolition is near completion. Mechanical/Electrical work has commenced.
- Level 4 North: Punch List Review is scheduled for mid-February. Mechanical/Electrical
work is near completion. Finish painting & ceilings are near completion.
- Level 4 South: Scheduled to commence in March.
- Roofing: Work has commenced and near completion on the north side. Work has been delayed
due to the weather.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
The Craig Hall under slab ductwork replacement is wrapping up at the north side of
the lobby. Craig Hall terrazzo slab preparation work continues. The new building exterior
water proofing continues. The new building interior framing continues. The new building
mechanical, electrical, and plumbing rough-in continues. The new building masonry
veneer installation continues at the north façade. The new building glass is being
installed at the lobby curtainwall.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The 4th floor is complete and the office furniture has been installed. The 1st floor
clinic area is complete. There are some wall coverings that need to be installed due
to a manufacturer’s error. The wall coverings will be delivered mid-February. The
air handling unit installation is complete. They are completing a test and balance.
Demolition on the 2nd and 3rd floor offices has begun. The clinic is operational.
Work on punch list items will continue while the clinic is operational.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
The contractor is currently working on a few punch list items.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Interior framing continues along the main first floor corridor and offices. Drywall
work continues around the Event Hall. Interior electrical, mechanical, and plumbing
rough-in continues throughout the building. Glass installation continues around the
building exterior. Exterior terracotta cladding sub framing installation continues
around the building.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The weather has stalled work on the exterior. Work will resume on the last section
on the North side and West side. The Contractor continues to work on real sealing
the windows and construction joints on each floor. The remaining lighting protection
will be installed this month, and the roof replacement will begin by late February.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Ceilings installation is nearing completion in all office areas. Fire alarm devices
are installed in the office areas and painting in offices is almost complete. The
storefront framing is being installed this week, and glass will be installed next
week. The flooring installation is almost complete in office areas. The mezzanine
wall in the lobby has been removed, and structural steel installation is nearly complete.
Door and door hardware installation will be complete this week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make site visits for verifications. Submittal
review continues. Selective demolition has occurred.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
The new column and lintel structure has been installed. Wall plaster repair, electrical,
and hallway HVAC installation are ongoing. Framing and sheetrock work began this
week.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Metal wall framing continues and drywall installation is starting. HVAC installation
is in progress. Submittal reviews are in progress. Anticipated project completion
is at the end of the Spring 2026 semester.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
The concrete path and repair work on the courtyard side of the east and south elevations
of Freudenberger House continue. Contractors will be proceeding with the painting
portion of their work as temperatures allow. Work will continue into the summer.
Printable weekly updates
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026
- December 19, 2025
- December 12, 2025
- December 5, 2025
- November 21, 2025
- November 14, 2025
- November 7, 2025
- October 31, 2025
- October 24, 2025
- October 17, 2025
- October 10, 2025
- October 3, 2025