Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending November 6, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the interior steel panel installation continues. Acoustical wood panel
preparation continues in Coger Theatre. The exterior ramp and stair concrete have
been poured, and exterior site work continues. In the new addition, wood cladding
installation is nearly complete at the south side doors. In the new building, punch
list work is nearly complete, along with installation of audio-visual equipment in
the Studio Theatre.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The display case installation is nearly complete. Lobby 109 feature wall installation
continues, as well as remaining punch list work. Preparations are being made for
the grand opening events.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Finishes such as flooring, paint, doors, lights, and ceiling installation are nearly
complete in all areas. The new hydronic and steam piping has been installed and will
be connected to the existing building system. The new wayfinding and room signs are
being installed next week. The new water fountain was installed on level 2 this week,
and the new level 2 restrooms are nearing completion. The new Automatic Transfer Switch
(ATS) for emergency power will be installed over the weekend.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 is still offline, being retrofitted. Completion has been delayed until
early November. Cab finishes will be installed in early November once the elevator
is operational. Project is scheduled to be complete in January 2027.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Painting is nearing completion, while carpet and wall base installation are ongoing.
An initial punch meeting is scheduled for November 16. Furniture is scheduled for
installation the week of November 9, with move-in to occur the following week.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Roof work and precast cleaning and caulking are starting this week, with material
deliveries and precast cleaning of the penthouses. The window replacement scope of
the project is anticipated to start in February, pending shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
The Contractor has moved on-site and is starting sitework, preparing to install the
underground utilities. We are currently reviewing the schedule for the interior
work, and we continue to receive submittals for the project.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
Lead abatement is complete, and interior demolition is ongoing in the new mechanical
and locker room areas. Product submittals continue to come in and are being reviewed
by the consultants.
Printable weekly updates
- November 6, 2026
- October 30, 2026
- October 23, 2026
- October 16, 2026
- October 9, 2026
- October 2, 2026
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026