Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending October 9, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, interior steel panel installation continues to proceed and is near
completion. The exterior ramp, stair and site work continues. In the new building,
large double doors have been installed. Final punch list work continues along with
the audio-visual equipment in the Studio Theatre.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Wood wall panel installation is at the final stages of completion in Traditions Hall,
and installation of the display case has commenced. Furniture has been delivered,
and the lobby feature wall installation continues. First and second floor reception
desks have been installed, and punch list work continues. Stainless steel planter
installation is complete at the south end of the site and the new freestanding bear
head has been installed on the South lawn.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The power outage last weekend to install an automatic transfer switch and associated
electrical equipment was successful. There will be a cooling shutdown this week to
connect the new hydronic piping. Wall framing and drywall on level 1 are complete,
and ceiling grid installation is ongoing. Carpet and ceilings have been installed
in classrooms and labs on level 2. Sheetrock and wall base are being installed in
level 2 restrooms this week. Casework installation is nearly complete on both level
1 and level 2.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 has been taken offline. Demolition and replacement of the elevator continue.
The new AHU is completed. A valve was replaced due to lack of capacity. This elevator
is anticipated to be completed in late October.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They will be finishing on the south
side of the building this week, along with a few other touch-up areas. Then they
will begin working on the north side of the building.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Ceiling tile installation and wall repair are ongoing. Painting will continue through
mid-October.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Submittals are in progress for the project. Roof work and precast cleaning and caulking
are anticipated to start in October. The window replacement scope of the project is
anticipated to start in December, pending shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
The project kick-off meeting is scheduled to occur in early October. Discussions
are occurring with the Contractor and the client regarding coordination for the project.
Equipment is being procured.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
Construction fencing installation will begin October 15, and the Kings Street pedestrian
walkway will be closed. Please reference the closure notice for additional details. Lead abatement is ongoing and will continue throughout the
month.
Printable weekly updates
- October 9, 2026
- October 2, 2026
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026
- August 14, 2026
- August 7, 2026
- July 31, 2026
- July 24, 2026