Update for week ending July 3, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical & electrical commissioning continues. Completion for the mechanical systems
is expected next week. The West Mall restoration is complete. Audio-visual work is
complete. The auditorium seating and instructor table installation is scheduled for
mid-July. Final furnishings are being ordered. Furniture installation for the graduate
student office has commenced. For the existing building renovation, mechanical and
electrical work continues. Interior wall patching and painting continues. Exterior
concrete patching and cleaning continues.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
The Job Order Contractor work has commenced. Sections of sidewalk to be replaced include
Lot 25 at Bear Boulevard, Bear Shuttle Drive Bikeway at Scholars House and Harrison
Street, Southeast Corner of Blair-Shannon House, South Side of West Mall at JQH Parkway,
North Side of Ellis Hall, Lot 1 Center Sidewalk and Steps, Strong Hall Lot, Southwest
Corner Plaster Stadium, and the East Side of Hill Hall.
Replace Roof, Hammons Hall for the Performing Arts
Eric Easter, Project Manager
The project is complete.
Renovate Classrooms and Hallways, Greenwood Laboratory School
Chelsea Beck, Project Manager
Work in the hallways is nearly complete. Work continues on the current classroom renovation.
Third Floor Buildout, Jordan Valley Innovation Center
Shanon Mitchell, Project Manager
Epoxy floors, dryfall paint, and window shade installation are complete. Painting
continues throughout the project, HVAC tie-in pieces installation continues, and electrical
work is in progress for the window shades and light fixture installations.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Concrete block installation has commenced at the northwest stairs. Underground building
fire suppression installation continues. Underground sanitary line installation is
wrapping up. Craig Hall asbestos abatement continues.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
Walls have been framed. Electrical/conduit work is complete. Work is in progress with
the lighting fixtures. Mechanical ductwork is being installed. The new fire sprinkler
lines are being installed. Demolition on the 4th floor office spaces is complete.
Framing on the 4th floor has begun. Drywall continues. New exterior windows continue to be installed.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
The new skylights are expected to be delivered mid-August. The new roof has been installed.
The Contractor will finish sealing the capstones this week. The gravel flood coat
will be installed after the skylights are installed.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Concrete walls are being formed and poured around the perimeter of the building. Underslab
plumbing installation continues. Underground chilled water piping is wrapping up,
and the Contractor is preparing for concrete and asphalt.
Lighting Improvements, Plaster Stadium
Bethany Henry, Project Manager
Installation of the new data communication wiring will be complete this week. The
Contractor is working on programing the light show to the selected music clips. It
is anticipated that light start-up will occur next week.
Renovate Chick-Fil-A, Plaster Student Union
Chelsea Beck, Project Manager
The ceiling tile, millwork, and lighting installation are complete. Flooring and wall
tile will begin next week.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The Contractors are preparing to mobilize in August.
Infrastructure Support for Broadcasting, Plaster Stadium
Bethany Henry, Project Manager
Boring across Grand Street for new power continues. The City Utilities utility vault
has been set on the south side of Grand Street. Installation of new underground conduits
for the parking lot lights will occur this week. New roofing is being installed on
the press box roof.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Construction in phase 1 areas (basement, east side of first floor, and mezzanine)
is underway and will continue until Spring of 2026. Demolition of flooring in the
basement and on the mezzanine level is complete. The demolition of flooring on the
first floor (under the mezzanine and in the lobby) is underway and will wrap up next
week. Demolition of walls, doors, ceilings, etc. will begin this week on the mezzanine.
Construction in phase 2 areas (west side of first floor and second floor) will begin
in Spring of 2026.
Printable weekly updates
- July 3, 2025
- June 27, 2025
- June 20, 2025
- June 13, 2025
- June 6, 2025
- May 30, 2025
- May 23, 2025
- May 16, 2025
- May 9, 2025
- May 2, 2025
- April 25, 2025
- April 18, 2025
- April 11, 2025
- April 4, 2025