Update for week ending November 14, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
Mechanical and electrical commissioning is complete except for two items which are
in process of completion. The Project Engineer is working with the Commissioning Agent
and JCI to identify the issues with completion. Final furnishings installation is
complete except for one item. Interior building signage and monument signage lighting
final installation are scheduled for mid-November. Strobic fan silencers are scheduled
to be installed the week of Thanksgiving. Remaining items are currently being addressed
and are near completion. Phase I is scheduled to be complete by the end of December. For
the existing building renovation (Phase II):
- Level 1: Mechanical and electrical work is nearing completion. Rooms are nearing completion,
pending the lab moves to complete the work. Lab shifts are in progress. Door and hardware
installation have commenced.
- Level 2: South: Substantially complete except for ceiling tile placement. Door and
hardware installation have commenced. Floor polishing is complete.
- Level 2: North: Mechanical and electrical work is nearing completion. Rooms nearing
completion. Corridors are nearing completion. Floor polishing is complete.
- Level 3: South: Substantially complete except for ceiling tile placement, doors and
hardware.
- Level 4: North: Room demolition continues. Mechanical and electrical work has commenced.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
The Craig Hall addition concrete slab pour is complete. Craig Hall interior MEP rough-in
continues. Excavation continues within Craig Hall for the new ADA ramp on the north
side of Coger Theatre. Exterior framing continues around the perimeter of the building.
The Black Box Theatre Mezzanine and main stair landing concrete have been poured.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The contractor is working on punch list items. Additional floor prep is needed in
some areas where the carpet is being installed. The glass doors are being installed.
The wooden doors have been painted and installed. The remaining sound booth has been
installed. Painting on the 1st floor is nearing completion.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
All skylight and roof work is complete. Drywall repairs are being scheduled.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Exterior framing and sheathing installation continue throughout the building. Interior
framing continues. Interior electrical wall rough-in continues. Roof installation
continues at the Event Center.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
Work crews have moved to the last section on the North side and West side of the building.
All previous work on the North and West side is complete. Work continues on real
sealing the windows and construction joints on each floor.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Drywall finishing is on-going at the Mezzanine level and painting has begun on north
end. Duct supports and steel supports have been installed between Level 1 and the
Mezzanine. Door frames are being installed on Level 1 next week and FCU installation
has begun. The wall framing on Level 1 is nearly complete and MEP rough-in has started.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator Contractor has conducted their preliminary field survey. We are working
on getting submittals from the Contractor.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
Flooring and pipe insulation remediation has been completed. Coordination meetings
occurred this week to discuss the final remediation required at the exterior walls
within the suite. The General Contractor will disconnect and remove items on the
exterior walls, to include conduit and wall heater units this week. Asbestos abatement
will resume next week.
Printable weekly updates
- November 14, 2025
- November 7, 2025
- October 31, 2025
- October 24, 2025
- October 17, 2025
- October 10, 2025
- October 3, 2025
- September 26, 2025
- September 19, 2025
- September 12, 2025
- September 5, 2025
- August 29, 2025
- August 22, 2025
- August 15, 2025
- August 8, 2025
- August 1, 2025