Update for week ending March 20, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical & Electrical Commissioning is on track for completion. The final visit
with the Commissioning Agent is being scheduled. Final furnishings will be installed
by the middle of May. A preliminary list of warranty items has been submitted by consultants
for review. The schedule for completion is pending.
For the existing building renovation (Phase II):
- Level 1, 2, & 3 South: Mechanical/Electrical work is complete except for commissioning.
Door/hardware is still pending due to door delays. Card access to follow.
- Level 3 North: Mechanical/Electrical work continues. Room finishes continue. Ceiling
grid work has commenced. Completion is scheduled for late April with moves scheduled
for the first two weeks of May.
- Level 4 North: Mechanical/Electrical work is complete except for commissioning. Preliminary
checklists are underway.
- Level 4 South: Demolition is near completion. Electrical/Mechanical work has commenced.
- Atrium: Work on the ceiling is complete. Scaffolding has been removed and replaced
at the south window wall to complete work.
- Roofing: the south side roofing has commenced.
- Exterior: Landscaping is scheduled to commence mid-April/May. Briggs Street final
asphalt topping is scheduled for June.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Craig Hall interior ramp work continues. Craig Hall terrazzo installation continues.
Craig Hall painting is wrapping up at the second floor. Craig Hall drywall installation
continues at the first floor. The new building drywall installation continues throughout
the building. The new building mechanical, electrical, and plumbing rough-in continues.
The new building masonry veneer installation continues at the north façade. Awaiting
remaining exterior glass units for the new building.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The punch list items are being completed. The 3rd floor is almost complete, and the
2nd floor is wrapping up. The Contractor will be removing the construction fencing
and will be reseeding next week. A punch list review will occur later in April.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
This project is complete.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing continue throughout the Event Hall and at the second-floor
offices. Interior mechanical, electrical, and plumbing rough-in continue throughout
the building. Awaiting the remaining exterior glass units. Exterior terracotta cladding
sub framing installation continues. Window trim/flashing installation continues at
the east façade.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The work on the exterior is complete. The roofing portion of the work is continuing
as planned.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Phase one is substantially complete, and the Mathematics Department and Computer Science
Department moved into their new offices this week. The fire alarm was successfully
tested and the HVAC testing and balancing is underway. Minor work in the basement
and classroom 151 will be complete by the end of this week. Painting and flooring
installation is nearly complete in the lobby and common areas. Furniture installation
in the lobby and common areas will occur next week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make periodic site visits for verifications.
Submittal reviews continue.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
Hydronic pipe insulation work continues. Wall patching and corrective plaster work
around the windows is in progress. A portion of the delayed control valves arrived
on site this week. These valves are scheduled for installation, and there will be
a pressure test upon installation. Next week, work will include the installation
of the ceiling grid, further electrical work, painting, and tentatively the installation
of the millwork and fire alarm.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
Overhead mechanical, electrical, and plumbing work and drywall is completing this
week, and painting has begun. Project completion is anticipated for mid-May.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
Concrete patch and repair work continues on the west wing courtyard side and east
wing east side of Freudenberger House. The Contractor continues to have good weather
for painting. The Contractor continues to work at Blair-Shannon House on the south
elevations. The work will continue into Summer 2026.
Printable weekly updates
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 13, 2026
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026
- December 19, 2025
- December 12, 2025
- December 5, 2025