Update for week ending December 19, 2025
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
Mechanical and electrical commissioning continues to be on hold due to graphics issues.
The process to complete commissioning has been established but no dates have been
confirmed yet. Final Link furnishings installation is complete. Monument signage
lighting final installation is pending. A short list of items remain and are currently
being addressed and scheduled. Remaining project items are forecasted to be complete
by the end of December except for additional items to be funded by remaining project
budget.
For the existing building renovation (Phase II):
Level 1 mechanical/electrical work is nearly complete. Level 1 lab shifts are complete.
The next shift is scheduled for next week. Level 1 door/hardware has commenced and
is ongoing. Level 2 South is substantially complete except for lab entry painting
and tackboard. Level 2 South door/hardware installation commenced and is ongoing.
Level 2 North mechanical/electrical work is near completion. Level 2 North office
moves have commenced. Lab moves are scheduled for next week. Level 2 North corridors
are near completion. Level 3 South is substantially complete except for lab entry
painting, tackboard and doors/hardware. Level 3 North demolition is scheduled to
commence next week. Level 4 North room demolition continues. Level 4 North mechanical/electrical
work has commenced. Roofing work commenced this week.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
The Craig Hall addition concrete block installation continues. The Craig Hall interior
MEP rough-in is wrapping up. Exterior framing and sheathing continue around the perimeter
of the new building. Overhead mechanical, electrical and plumbing rough-in continues
in the new building. The second-floor interior framing continues in the new building.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The 4th floor is complete. Ceramic tile and LVT is completed. Floor prep is complete.
Carpet is being installed. Glass doors have been installed. The contractor continues
to touch up paint on all areas. The Fry Reglet’s have been installed, and they are
working on installing the wall coverings. They have started demo on the 3rd floor
offices. Anticipated move in date for 1st floor is mid-January.
Replace Skylights, Plaster Student Union
Eric Easter, Project Manager
All Skylight and roof work had been completed. Drywall repairs have started.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The exterior framing is wrapping up, and sheathing installation continues throughout
building. Interior framing continues. Drywall installation in the Event Center continues.
Interior electrical, mechanical and plumbing rough-in continues throughout building.
Roof installation continues at the eastern side of the building. Curtainwall installation
is wrapping up at the north and south entry and west along the event lawn. Exterior
weather barrier and liquid flashing installation continue around building.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The crews have moved to the last section on the North side and West side. All previous
work on the North and West is completed. They continue to work on resealing the windows
and construction joints and each floor, recent rain has slowed their progress on these
sides.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The ceiling grid and light fixture installation on the mezzanine level is on-going
and installation started this week on the Level 1. Wall framing for the basement electrical
room is complete, and ceilings have been removed to install piping over the basement
classroom. The overhead piping, HVAC, and in-wall piping installation is nearly complete
on Level 1. Drywall finishing and painting will continue for several weeks. Shoring
and demolition for the lobby area will begin next week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator contractor continues to make site visits for verifications. We are
currently working on reviewing submittals from the contractor. Selective demolition
will take place over winter break to determine if concrete masonry unit walls will
need reinforcing for installation of new hoist beam.
Renovate Suite 113, Carrington Hall
Tanya Garretson, Project Manager
The demolition of ceiling grid, soffit, and millwork has been completed. Mechanical,
electrical, and ductwork demolition are underway and will continue through the end
of the year. Rough-in has started in selective areas and will be the focus beginning
in January.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The project construction kick-off meeting was held on December 4th. The contractor
is scheduled to mobilize and begin demo of walls and floors starting the week of December
8th and then proceed with demo of plumbing and electrical. Submittal reviews are in
progress. Anticipated project completion is the end of the Spring 2026 semester.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
The project construction kick-off meeting was held on December 3rd. The contractor
is scheduled to mobilize the week of December 22nd. The project will continue into
summer 2026.
Printable weekly updates
- December 19, 2025
- December 12, 2025
- December 5, 2025
- November 21, 2025
- November 14, 2025
- November 7, 2025
- October 31, 2025
- October 24, 2025
- October 17, 2025
- October 10, 2025
- October 3, 2025
- September 26, 2025