Update for week ending June 26, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
-
- Mechanical and Electrical Commissioning for Phase 1 & 1A: Remaining items are ready
for final testing by the commissioning agent.
- Warranty items have been completed. A report on remaining items has been issued with
a response requested for next week.
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4: Mechanical/Electrical are complete except for commissioning.
Corrections are ongoing. Door/hardware near completion. Card access on all floors
is scheduled to be complete by the end of next week. Fume hood installation is complete
and ready for calibration.
- Atrium: New domes have been installed.
- Roofing: The schedule has been delayed due to weather.
- Exterior: Landscaping has commenced. The Briggs Street final asphalt topping is scheduled
for mid-July.
- Other: The replacement elevator installation is nearing completion, and the inspection
has been scheduled for early July.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, elevator installation is near completion and lobby light fixture installation
continues. Second floor door and hardware installation is near completion. Existing
wood acoustical panel demolition is complete, and the interior acoustical wood paneling
installation has commenced. On the exterior, concrete site wall formwork installation
for the new exterior ramp is complete. Curb and gutter have been poured along Grand
Street and sidewalk pour is planned for the end of this week, weather permitting.
New building drywall installation, finishing and painting continues on the first floor.
Elevator installation is complete and the ceiling tile, electrical and audio-visual
fixtures installation is nearing completion on the second floor. Phenix marble cladding
installation is nearing completion, and the exterior metal soffit panel installation
continues.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The Contractor is working on completing punch list items. We are pursuing some additional
upgrades to the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Exterior terracotta cladding installation continues in the Event Center. Interior
terracotta installation continues. Phenix marble installation is nearing completion
at the east façade. Painting continues throughout the first floor. Second floor
office storefront glass installation is complete, and the storefront has been installed
at the second floor conference rooms. Cabinets have been installed in the Event Center
catering kitchen. Wood ceiling installation continues at the main corridor. Acoustical
wood panel installation continues in the Event Center. Lot 27 work continues. Excavation
and underground storm water piping installation is complete at the Event Lawn.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The project is substantially complete.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The intermediate slab (abandoned concrete roof deck) that was discovered between level
1 and level 2 has been removed. Wall framing continues on level 1 along with MEP rough-in,
and drywall installation continues on level 1. Drywall installation on level 2 is
complete and MEP rough-in is nearly complete. This includes overhead ductwork, VAV
box installation, mechanical piping, and electrical work. Power has been turned off
on level 3, and a new electrical closet is being constructed. Mechanical piping is
being installed in the vertical chase near the elevator to serve several areas of
renovation.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The new fan coil unit will be installed next week. Elevator work continues and it
will be shut down Monday through Wednesday of next week.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The Contractor is working on punch list items. This project is substantially complete.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
The project is substantially complete.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor is working on ductwork installation, new lighting, control wiring,
and painting. Anticipated project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on the west side of Strong Hall. It is anticipated
that work will be completed by October.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
Lots 21, 35 and 44 are substantially complete, as well as Bear Park South. Bear Park
North is currently being cleaned and is scheduled for new striping early next week.
All work is weather-dependent, and schedules may change. Please do not move, walk,
or drive around barricades, cones, or other traffic safety equipment. Please refer
to the Administrative Services Notifications Blog for more information on closures.
Printable weekly updates
- June 26, 2026
- June 19, 2026
- June 12, 2026
- June 5, 2026
- May 29, 2026
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026