Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending August 7, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
- Commissioning for Phase 1 & 1A is complete.
- Warranty items: Project team discussed remaining items last week. Final warranty
date for the mechanical system has been established. Documents are being routed for
signatures.
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4: Mechanical/Electrical are complete. Final commissioning to commence
next week. Card access installation on all floors is complete. Fume hood certification
is complete. All offices, labs and support spaces are complete except for storage
areas being utilized by construction. A punchlist walk was held this week. Remaining
items are being worked on this week and are scheduled to be done next week.
- Exterior: Lot 18A rework has been rescheduled for August 14 and work will take at
least a week to complete.
- Other: Landscaping and irrigation system corrections are underway.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall the interior acoustical wood panel installation continues. The storage
rack has been installed and equipment delivered to the building. Coger Theatre ceiling
painting is nearly complete and audio visual owner training for Room 206 has been
performed. The exterior concrete site wall formwork is nearly complete. In the new
building, terrazzo installation continues in the lobby. Audio visual suspension grid
is being installed in the Black Box Theatre. Final wall painting continues at the
second floor and exterior metal cladding installation continues. Carrington Avenue
sidewalk work is nearing completion in order to be open for fall semester. The Grand
Street crosswalk remains open.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Exterior terracotta cladding installation remains to be completed at the courtyard.
Wood wall panel installation continues as well as the glass railing and handrail installation.
Terrazzo installation is nearing completion with the final grind and polishing yet
to be completed. The second-floor office suite is nearly complete. Carpet installation
is nearing completion at the first-floor office suite. Office furniture installation
is scheduled for August 17. The new parking lot asphalt and striping is complete,
and Lot 27 is open for use. Site work continues around the Event Lawn. The new concrete
drive from Bear Boulevard is to be completed this week. Formwork for the sidewalks
around the site has been installed and awaiting concrete.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The new heat exchanger was moved into the basement, and the new chilled water piping
has been installed in the basement mechanical room. Wall framing is nearly complete
on level 1, and drywall installation and MEP rough-in is underway. The two new air
handler units have been installed in the level 2 mechanical room and steel installation
for slab openings is complete. MEP rough-in on level 2 is nearly complete and ceiling
grid installation is underway.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator has passed inspection, and it will be available for use during move-in
next week. Work continues to troubleshoot issues with the phone lines, and the elevator
cab finishes are to be installed after move-in. Elevator 25 will be taken offline
the week after school starts.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
Project is complete with minor punchlist items to address.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed the work on the
roof and 4th floor and have made their way to the south side of the building. They
will continue working their way around the building utilizing smaller lifts. The
work is anticipated to be complete by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Abatement work continues. Construction work is scheduled to begin on August 17.
Printable weekly updates
- August 7, 2026
- July 31, 2026
- July 24, 2026
- July 17, 2026
- July 10, 2026
- July 3, 2026
- June 26, 2026
- June 19, 2026
- June 12, 2026
- June 5, 2026
- May 29, 2026