Weekly Project Updates

Weeky Project Updates

Planning, Design and Construction is pleased to share weekly project updates with the campus and community. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates, and previous updates are available at the bottom of this page.

If you would like additional details or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.

Update for week ending November 20, 2026

A printable version of our Weekly Project Updates is available.

Judith Enyeart Reynolds Complex

Michael Mardis, Project Manager

In Craig Hall, the interior steel panel installation continues.  Acoustical wood panel preparation continues in Coger Theatre.  The exterior ramp and stair concrete have been poured, and exterior site work continues.  Remaining punch list items in the new building continue to be addressed.

Renovation, Cheek Hall

Adam Shuler, Project Manager

A new trash enclosure and service drive are being constructed between Cheek Hall and Wells House. The area will remain closed for the next few weeks while work is being completed. All new HVAC systems are operational for phase 2, and controls are being adjusted to accommodate. The new wayfinding and room signs are being installed in phase 2 areas in the coming weeks. The new level 2 restrooms are nearing completion, and final finishes are being installed in other phase 2 areas.

Update Elevators 24, 25, & 26, Hammons House

Eric Easter, Project Manager

Elevator 25 is still offline, being retrofitted.  Completion has been delayed until late November.  Cab finishes will be installed after the elevator has been retrofitted.  The project is scheduled to be completed in January 2027.

Renovate Rooms 422 & 424, Carrington Hall 

Tanya Garretson, Project Manager

The project is substantially complete, and staff moved in on November 18.  Remaining punch list items will continue to be addressed.

Exterior Renovation, Glass Hall 

Shanon Mitchell, Project Manager

Roof work and precast cleaning and caulking are in progress. The window replacement scope of the project is anticipated to start in February, pending shipment of materials. 

Install Cooling Tower & Process Piping, JVIC Building 6

Eric Easter, Project Manager

The Contractor has mobilized on-site and begun sitework in preparation for the installation of underground utilities.  There has been a slight delay in the boring process, but the Contractor finished boring this week.  Due to the delay in boring, the Contractor will be moving to interior work next week.  We continue to receive submittals for the project, and they are being reviewed by the project team. 

Renovation for Football Locker Room, McDonald Arena

Danielle Palmer, Project Manager

Interior demolition continues in the renovation areas. Product submittals continue to be submitted and are being reviewed by the design consultants and campus team. Electrical infrastructure upgrades along Kings Ave. are scheduled to begin next week.

Printable weekly updates