Weekly Project Updates

Weeky Project Updates

Planning, Design and Construction is pleased to share weekly project updates with the campus and community. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates and previous updates are available at the bottom of this page.

If you would like additional details or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.

Update for week ending September 12, 2025

A printable version of our Weekly Project Updates is available.

Addition & Renovation, Blunt Hall

Laura Derrick, Project Manager

Mechanical and electrical commissioning is complete except for two items which will be completed in the next two weeks. Final furnishings installation continues. Furniture installation for the graduate student office is to be completed in September.  Interior building signage has been removed due to fabrication issues. The monument sign installation is complete. The dedication of the new addition will occur on September 12. For the existing building renovation, Level 2 & 3 South are substantially complete except for office ceilings and corridors. Mechanical & electrical continues on Level 2 North and Level 1. Air handling units start-up and commissioning has commenced. Wall patching and painting have commenced on Level 2 North and Level 1. Phase 2B (Levels 2 & 4 North and Level 1) are scheduled to be completed in December.

Third Floor Buildout, Jordan Valley Innovation Center

Shanon Mitchell, Project Manager

The punch list review is taking place this week, and substantial completion will be issued.

Judith Enyeart Reynolds Complex

Michael Mardis, Project Manager

Steel erection continues. Craig Hall addition concrete wall formwork is being installed. Craig Hall underslab mechanical, electrical, and plumbing rough-in continues. Framing is complete in the second floor acting studio and costume storage area.

Phase II Renovation, Kampeter Health Sciences Hall

Eric Easter, Project Manager

The exterior windows are being installed. Electrical/conduit work is complete. Work is in progress with the lighting fixtures. Ceiling dry fall is complete.  Painting is progressing on the first floor. The cable trays are installed. The fourth floor walls are being painted. The drop ceiling is being installed. Store fronts have been installed. 

Replace Skylights, Plaster Student Union

Eric Easter, Project Manager

All skylights have been installed, the demoed material will be removed this week, and the completion of the roof will take place next week.

Clifton M. Smart III Advancement Center

Michael Mardis, Project Manager

Steel erection will continue through mid-September. Exterior wall framing for the event center is starting next week. Mockup concrete foundation work is complete.

Lighting Improvements, Plaster Stadium

Bethany Henry, Project Manager

The field lights are operational, and training has been completed. Minor adjustments to the egress fixtures are currently in progress.

Replace Roof and Tuckpointing, Sunvilla Tower

Eric Easter, Project Manager

The Contractor has installed the swing stage, and has begun the resealing of the window.

Infrastructure Support for Broadcasting, Plaster Stadium

Bethany Henry, Project Manager

Final termination of wiring infrastructure is in process. Punch list items are being corrected.

Renovation, Cheek Hall

Adam Shuler, Project Manager

The basement selective demolition for the new electrical room has been completed. The remaining abatement of flooring materials was completed this week. Saw cutting slab and plumbing rough-in will begin on the first floor at the end of this week. Mezzanine framing and overhead mechanical, electrical, and plumbing rough-in will be completed in the coming weeks.

Printable weekly updates