Update for week ending June 12, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
- Mechanical and Electrical Commissioning for Phase 1 & 1A: Consistent issues persist.
Three items remain on the punch list, as well as completing deliverables.
- Pit furniture installation is complete.
- Warranty items have been completed.
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4 (North): Mechanical/Electrical are complete except for commissioning.
Corrections are ongoing. Door/hardware near completion. Card Access on fourth floor
is ongoing. Fume hood installation is nearing completion.
- Level 4 (South): Mechanical/Electrical punch list walk through is scheduled for mid-June.
- Atrium: New dome lighting and domes are pending completion.
- Roofing: The schedule has been delayed to mid-June due to weather.
- Exterior: Landscaping has commenced. The Briggs Street final asphalt topping is scheduled
for mid-July.
- Other: The replacement elevator installation has commenced, and the inspection has
been scheduled for early July.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
Mechanical, electrical, and plumbing installation is nearing completion in the scene
shop addition. In Craig Hall, interior storefront and glass has been installed at
the student lounge. Elevator installation continues. Terrazzo installation is complete
and polishing remains. Lobby light fixture installation continues. Second floor
door and hardware installation continues. Existing wood acoustical panel demolition
in Coger Theatre continues. On the exterior, concrete site wall formwork installation
for the new exterior ramp continues. Excavation and grading along Grand Street continues.
New building drywall installation and finishing continue on the first floor. Elevator
installation is complete. Ceiling tile, electrical and audio/visual fixtures are
being installed. Phenix marble cladding installation continues at the south façade
as well as the interior lobby.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The Contractor is working on completing punch list items. We are pursuing some additional
upgrades to the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Drywall installation and finishing is nearing completion on the first floor. Network
cabling installation is nearing completion. Exterior terracotta cladding installation
continues at the Event Center. Interior terracotta installation continues. Phenix
marble installation continues on the east façade. Terrazzo installation is complete
on the second floor, and polishing remains. Painting continues throughout the first
floor. Second floor office storefront glass installation is nearing completion.
Wood ceiling installation continues on the second floor conference room. The Event
Center air handling unit is operational. Acoustical wood wall panel installation
continues in the Event Center. Lot 27 underground utility work continues. Excavation
and underground storm water piping installation has commenced at the Event Lawn.
Replace Roof and Tuckpointing, Sunvilla Tower
Eric Easter, Project Manager
The project is substantially complete. We have added additional upgrades to the awning.
Color selection to match the existing awning, and fabrication will begin soon.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Wall framing continues on level 1 along with MEP rough-in. An intermediate slab (abandoned
concrete roof deck) was discovered between level 1 and level 2, and it is being removed.
Drywall installation on level 2 is nearing completion and MEP rough-in is underway.
This includes overhead ductwork, VAV box installation, mechanical piping, and electrical
work. Power has been turned off on level 3, and a new electrical closet is being constructed.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The new beam is installed, and the elevator has now been taken offline. The crane
pick was successful. The Contractor continues to demolish the elevator and they have
completed the installation of the structural supports.
Drago Hall Renovation, West Plains
Shanon Mitchell, Project Manager
The Contractor is working on punch list items. This project is substantially complete.
Exterior Ledges Repair, Freudenberger and Blair-Shannon House
Shanon Mitchell, Project Manager
The Contractor is completing remaining work this week.
Kitchen Lighting & HVAC Upgrades, Blair-Shannon Dining Center
Shanon Mitchell, Project Manager
The Contractor is installing new ductwork and new electrical for the new HVAC units.
Anticipated project completion is mid-July.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor has started work on the west side of Strong Hall. The work is anticipated
to be complete in October.
FY26 Parking Lot Maintenance, Springfield Campus
Joey Hamm, Project Manager
Work is still progressing with the majority now complete. In Lots 21, 35 and 44 asphalt
repairs have been completed, the surface resealed and painted. Remaining work includes
installing concrete wheel stops, new ADA signs, and other miscellaneous items. Portions
of the lots will need to be closed for this work to take place. Lot 21 work is scheduled
to begin on Monday, June 15 and Lot 35 work is scheduled to begin on Monday, June
22. Bear Park South is scheduled to be closed June 15 through June 25 for cleaning,
restriping and safety painting. Bear Park North is scheduled to be closed June 24
through July 3 for cleaning, restriping and safety painting. All work is weather
dependent and schedules may change. Please do not move or drive around barricades
at lot entrances. Refer to the Administrative Services Notifications Blog for more information on closures.
Printable weekly updates
- June 12, 2026
- June 5, 2026
- May 29, 2026
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 2, 2026