Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending September 18, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the terrazzo floor polishing continues. The exterior ramp and exterior
site work continue. In the new building, wood cladding installation continues. The
new building is substantially complete, and the punchlist review will commence after
the dedication.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds. The contractor has been making repairs
for reported items identified in recent weeks.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Wood wall panel installation continues in Traditions Hall. The Lobby 109 feature
wall installation continues. Installation of the bear head light fixture continues
in the Bears Den. Installation of the stone surround at the fireplace continues.
Landscaping is nearly complete. Move-in is complete, and furniture installation is
nearly complete. Stainless steel planter installation continues at the south end
of the site.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The hydronic pipe installation is underway in the basement mechanical room along with
installation of the heat exchanger. The new automatic transfer switch and associated
electrical equipment will be installed next week. Wall framing and drywall on level
1 is mostly complete, and ceiling grid installation is ongoing. MEP rough-in on level
1 is nearing completion. The new data racks and cable installation are complete on
level 2. Plumbing installation for the level 2 restrooms has begun. MEP rough-in on
level 2 is nearly complete, and ceiling tile installation started this week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 has been taken offline. Demolition and replacement of the elevator continue,
along with commissioning of the new air handler. Installation of the new fire alarm
features has begun.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed the work on the
roof, fourth and third floors. They are now working on the second and ground floors.
Work is anticipated to be complete by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Demolition of telecommunications and ceiling tile is complete, as well as electrical
work. Painting and trimming are underway.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Submittals are in progress for the project. Roof work and precast cleaning and caulking
are anticipated to start in October. The window replacement scope of the project is
anticipated to start in December, pending shipment of materials.
Printable weekly updates
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026
- August 14, 2026
- August 7, 2026
- July 31, 2026
- July 24, 2026
- July 17, 2026
- July 10, 2026
- July 3, 2026