Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending September 11, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the terrazzo floor polishing continues. The exterior paver base installation
continues, as well as ramp grading and topsoil installation throughout the site.
In the new building, the new sprung dance floor installation continues in the Black
Box Theatre. Exterior cladding closure panels are being installed. Interior wood
panel installation continues, and the performance classroom mirrors have been installed.
Carpet and base have been installed on the second floor, and the final painting is
nearly complete on the second floor.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds. The contractor has been making repairs
for reported items identified in recent weeks.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Wood wall panel installation continues in Traditions Hall. The Lobby 109 feature
wall installation continues. Installation of the bear head light fixture as well as
interior stone installation continues in the Bears Den. Move-in is complete as furniture
deliveries continue. Audio-visual installation in the executive boardroom is nearly
complete. Installation of topsoil and landscaping continues throughout the site.
Stainless steel planters are being installed at the south end of the site.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The new heat exchanger installation is underway in the basement mechanical room along
with hydronic pipe installation. Wall framing on level 1 is nearly complete, and ceiling
grid installation is ongoing. Drywall installation continues on level 1, and MEP rough-in
is underway. The new data racks and cable installation have started in phase 2 areas.
Plumbing installation for the level 2 restrooms has begun. MEP rough-in on level 2
is nearly complete, and ceiling tile installation will start next week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 has been taken offline. The contractor will continue demolition of the
elevator, prepping for a crane pick next week to remove the old elevator and bring
up the associated new assemblies.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed the work on the
roof, fourth and third floors. They are now working on the second and ground floors.
Work is anticipated to be complete by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Ceiling tile removal and electrical work are ongoing. Walls are being patched. Telecom
demolition began this week.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Submittals are in progress for the project. Field verification and measurements for
glass replacement started last week. Roof work and precast cleaning and caulking are
anticipated to start in October. The window replacement scope of the project is anticipated
to start in December, pending shipment of materials.
Printable weekly updates
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026
- August 14, 2026
- August 7, 2026
- July 31, 2026
- July 24, 2026
- July 17, 2026
- July 10, 2026
- July 3, 2026
- June 26, 2026