Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending September 25, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the terrazzo floor polishing is nearly complete and interior steel
panel installation continues. The exterior ramp, stair and site work continues.
In the new building, wood cladding is complete on the west side, and the large double
door frame installation has commenced.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds. The contractor has been making repairs
for reported items identified in recent weeks.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
Wood wall panel installation continues in Traditions Hall. The Lobby 109 feature
wall installation continues. Installation of the bear head light fixture continues
in the Bears Den. Installation of the stone surround at the fireplace is complete.
Landscaping installation is complete. Stainless steel planter installation continues
at the south end of the site.
Renovation, Cheek Hall
Adam Shuler, Project Manager
The hydronic pipe and heat exchanger installation in the basement mechanical room
is nearly complete. The new automatic transfer switch and associated electrical equipment
will be installed this week. Wall framing and drywall on level 1 is complete, and
ceiling grid installation is ongoing. MEP rough-in on level 1 is nearing completion,
and floor boxes have been installed. Carpet and ceilings have been installed in classrooms
and labs on level 2, and plumbing installation for the level 2 restrooms continues
this week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 has been taken offline. Demolition and replacement of the elevator continue.
Additional disconnects will need to be added per code requirements. This elevator
is anticipated to be completed in October.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed the work on the
roof, fourth and third floors. They are now working on the second and ground floors.
Work is anticipated to be complete by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Data installation and painting are underway.
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Submittals are in progress for the project. Roof work and precast cleaning and caulking
are anticipated to start in October. The window replacement scope of the project is
anticipated to start in December, pending shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
The project kick-off meeting is scheduled to occur in early October. Discussions
are occurring with the Contractor and the client regarding coordination for the project.
Equipment is being procured.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
The project kick-off meeting was held on September 23. The Contractor is developing
the construction schedule and finalizing site logistics. Construction and staging
are anticipated to begin in mid-October. Lead abatement began this week, and containment
barriers will remain in place throughout the abatement process.
Printable weekly updates
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026
- August 21, 2026
- August 14, 2026
- August 7, 2026
- July 31, 2026
- July 24, 2026
- July 17, 2026
- July 10, 2026