
Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates, and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending November 13, 2026
A printable version of our Weekly Project Updates is available.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall, the interior steel panel installation continues. Acoustical wood panel
preparation continues in Coger Theatre. The exterior ramp and stair concrete have
been poured, and exterior site work continues. Remaining punch list items in the
new building continue to be addressed.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The ribbon-cutting ceremony took place on November 11. Remaining punch list items
will be completed after homecoming.
Renovation, Cheek Hall
Adam Shuler, Project Manager
A new service drive is being constructed between Cheek Hall and Wells House, and pavement
is being poured this week and next. The new hydronic and steam piping has been installed
and connected to the existing building system. Heating has been restored to the building,
and controls are being adjusted to accommodate. The new wayfinding and room signs
are being installed this week on level 1 and level 2. The new level 2 restrooms are
nearing completion. The new Automatic Transfer Switch (ATS) for emergency power was
installed last weekend, and no issues were reported.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
Elevator 25 is still offline, being retrofitted. Completion has been delayed until
early November. Cab finishes will be installed in early November once the elevator
is operational. Project is scheduled to be complete in January 2027.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
A second punch list session has been scheduled for November 16. The suite is projected
to be complete at that time, except for the breakroom. Furniture installation is
nearing completion, and audio-visual installation is ongoing. Move-in has been shifted
to November 18 to accommodate department travel schedules
Exterior Renovation, Glass Hall
Shanon Mitchell, Project Manager
Roof work and precast cleaning and caulking are in progress. The window replacement
scope of the project is anticipated to start in February, pending shipment of materials.
Install Cooling Tower & Process Piping, JVIC Building 6
Eric Easter, Project Manager
The Contractor has mobilized on-site and begun sitework in preparation for the installation
of underground utilities. Several underground obstructions have caused delays in the
boring process. The Contractor anticipates transitioning to interior work next week.
Meanwhile, the project team is reviewing project submittals.
Renovation for Football Locker Room, McDonald Arena
Danielle Palmer, Project Manager
Interior demolition continues in the project areas. Product submittals continue to
be submitted and are under review by the design consultants and campus team.
Printable weekly updates
-
-
- November 13, 2026
- November 6, 2026
- October 30, 2026
- October 23, 2026
- October 16, 2026
- October 9, 2026
- October 2, 2026
- September 25, 2026
- September 18, 2026
- September 11, 2026
- September 4, 2026
- August 28, 2026