Weekly Project Updates

Planning, Design and Construction is pleased to share weekly project updates with
the campus and community. While not a comprehensive list, the updates reflect our
more substantial campus projects. Below are our most current updates and previous
updates are available at the bottom of this page.
If you would like additional details or information regarding a project not listed
below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@MissouriState.edu. Thank you for your interest in projects at Missouri State University.
Update for week ending August 14, 2026
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
For the building addition (Phase I):
For the existing building renovation (Phase II):
- Level 1, 2, 3, and 4: Mechanical/Electrical are complete. Remaining reported issues
are being addressed. Final commissioning was rescheduled for next week.
- Existing fume hood controls updates will be completed this week and then all fume
hoods in the addition and existing building will be fully functional.
- All offices, labs and support spaces are complete except for storage areas being utilized
by construction.
- Work continues on the remaining punchlist items and they are expected to be complete
by the end of next week, if not before.
- Exterior: Lot 18A rework has commenced and work will take two to three weeks to complete.
- Other: Landscaping is complete and irrigation system corrections are underway.
Judith Enyeart Reynolds Complex
Michael Mardis, Project Manager
In Craig Hall the interior acoustical wood panel installation continues at Coger Theatre
as well as the box office. New exterior door installation is nearing completion at
the north entrance. Second floor work is nearly complete in preparation for the start
of school. Casework and countertop installation continues in the student lounge and
box office and terrazzo floor polishing has commenced. The exterior concrete site
wall formwork is nearly complete. Topsoil and landscape installation has commenced
on the west side of the new building. In the new building, terrazzo installation
is complete in the lobby. Casework installation has commenced in the Design Studio
classroom. Audio visual suspension grid installation continues in the Black Box Theatre.
Final wall painting continues on the second floor, and floor prep is nearly complete
for the new sprung dance floors. Exterior metal cladding installation continues,
and the Grand Street Underpass will reopen on August 14.
Phase II Renovation, Kampeter Health Sciences Hall
Eric Easter, Project Manager
The project is substantially complete. We are pursuing some additional upgrades to
the facility with remaining contingency funds.
Clifton M. Smart III Advancement Center
Michael Mardis, Project Manager
The maroon exterior terracotta cladding installation is nearing completion at the
south elevation. Wood wall panel installation continues in Traditions Hall. Glass
railing and handrail installation continues. Final terrazzo grind and polishing remain
to be completed. First and second floor office desk and cubicle installation starts
on August 17. Exterior wood soffit panel installation has commenced. The new Bear
Boulevard south parking lot entrance reopened on August 13. Irrigation installation
is complete at the event lawn and topsoil has been laid along the Bear Boulevard parking
lot. Pavers have been installed at the northeast corner of the building.
Renovation, Cheek Hall
Adam Shuler, Project Manager
Wall framing and drywall installation is on-going on level 1, and MEP rough-in is
underway. The two new air handler units have been installed in the level 2 mechanical
room and ductwork is being adjusted to fit the layout. MEP rough-in on level 2 is
nearly complete and ceiling grid installation is underway. Signage in phase 1 areas
is being installed this week.
Update Elevators 24, 25, & 26, Hammons House
Eric Easter, Project Manager
The elevator has passed inspection and is in use. The cab finishes are to be installed
after move-in. They will take Elevator 25 offline the week after school starts.
Correct Water Infiltration, Strong Hall
Eric Easter, Project Manager
The Contractor continues work on Strong Hall. They have completed work on the roof
and 4th floor and will work their way around the building utilizing smaller lifts. The
work is anticipated to be complete by October.
Renovate Rooms 422 & 424, Carrington Hall
Tanya Garretson, Project Manager
Abatement work is complete and construction is scheduled to begin on August 17.
Printable weekly updates
- August 14, 2026
- August 7, 2026
- July 31, 2026
- July 24, 2026
- July 17, 2026
- July 10, 2026
- July 3, 2026
- June 26, 2026
- June 19, 2026
- June 12, 2026
- June 5, 2026