Update for week ending April 26, 2024
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
The level five (roof) concrete pour has been delayed to the end of next week due to
weather. Mechanical & electrical work continues on level zero, level one, level two,
and level three. Interior metal stud framing continues on level zero, level one, level
two and level three. Exterior metal stud framing continues. Topping out is scheduled
for May 22.
Autism Student Support Center, West Plains Campus
Adam Shuler, Project Manager
The structural steel installation continues, and all columns and roof trusses have
been installed. Steel installation will continue for the next several weeks. Steel
stud framing will start in the coming weeks with the parapet walls followed by roof
installation.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
The second concrete slab pour for level one is in place. The third concrete slab pour
preparation is in progress and is scheduled for next week, weather pending. Underground
electrical conduit and basement electrical equipment work continues. Under slab plumbing
trench drain work is in progress this week. Structural steel deliveries arrived this
week.
Agricultural Innovation Hub, Darr Agricultural Center
Shanon Mitchell, Project Manager
Concrete foundation work continues. Under slab electrical and plumbing work is in
progress.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Sidewalk replacement to commence the week after graduation in May.
MSU Baseball Training Facility
Adam Shuler, Project Manager
Drywall installation is nearing completion. Painting has started and will be complete
next week. Flooring and base installation will begin next week.
Turf Replacement, Allison South Stadium
Eric Easter, Project Manager
Submittals have been reviewed and approved. The contractor is securing materials for
the project. Work will commence after graduation in May.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
HVAC installation at the new locker room space, electrical work, wall framing, wall
clean up and prep at gym wall columns, and the removal of the bleachers in the north
gym is ongoing. Preparation for the upcoming installation of gym flooring is ongoing.
Further work in the north and south gyms, and the east and west decks will begin following
graduation in May.
Roof Replacement, Garst Dining Center
Eric Easter, Project Manager
Project submittals are being reviewed. The contractor is securing all of the materials
for the project. Work will commence after graduation in May.
Printable weekly updates
- April 26, 2024
- April 19, 2024
- April 12, 2024
- April 5, 2024
- March 29, 2024
- March 22, 2024
- March 15, 2024
- March 8, 2024
- March 1, 2024
- February 23, 2024
- February 16, 2024
- February 9, 2024
- February 2, 2024
- January 26, 2024
- January 19, 2024
- January 12, 2024