Fiscal Year 2014 (July 1, 2013-June 30, 2014)

Completion of Major Projects (>$100,000)

  • Stage Lift Replacement at Craig Hall
  • Carpet Replacement at Juanita K. Hammons Hall
  • Central Chilled Water System Connection for Meyer Library
  • Preventative Parking Lots Maintenance, Springfield Campus
  • Renovation and Addition to Gohn Hall, West Plains Campus
  • Chilled Water Loop Extension to Juanita K. Hammons Hall
  • Replace Pool HVAC System at Hammons Student Center
  • Reroof Sections of Juanita K. Hammons Hall
  • Renovate Suites 302 and 303 at Carrington Hall
  • Roof Replacement at Plaster Student Union
  • Jim D. Morris Basketball Complex at JQH Arena
  • Exterior Envelope Repairs at McQueary Family Health Sciences Hall
  • Expansion of the Wireless Network in Residence Halls
  • Replace Carpet on Multiple Floors in Glass Hall

Project Requests

198

Planning Design & Construction processed 198 Project Request Forms during fiscal year 2014.

2014 Project Request Forms chart

Consulting Services

42

Planning, Design & Construction awarded 42 Professional Services contracts during fiscal year 2014 with a contract value of $6,737,655.95.
(information updated 10/10/16)

Southwest Missouri Contractors

91%

91% of the construction contracts awarded in fiscal year 2014 by Planning, Design & Construction were with Southwest Missouri Contractors.

Construction Contracts

70

Planning, Design & Construction awarded 70 construction contracts in fiscal year 2014 with a contract value of $38,504,223.65.

2014 Construction Contracts chart

2014 Construction Awards